1 Jaunpur Welspun Kaveri Infraprojects JV 20068622 Baharaicha 6 10 4364 2022 2037 2052 26-Jul-2024 13-Oct-2025 13-Oct-2025 14-Oct-2025 Testing & Commissioning certificate, Road restoration, trial & run certificate and Final BOQ not signed by EE but TPIA checked and signed all document for further process. ok View
2 Jaunpur Welspun Kaveri Infraprojects JV 20020086 Bishambhara 2 3 1871 2022 2037 2021 22-May-2022 31-Dec-2024 20-Jun-2025 21-Jun-2025 Checked and found ok ok View
3 Jaunpur Welspun Kaveri Infraprojects JV 20089187 Gahlai 4 20 5620 2022 2037 2052 14-Sep-2024 18-Sep-2025 18-Sep-2025 19-Sep-2025 Checked and found ok. Ok View
4 Jaunpur Welspun Kaveri Infraprojects JV 20020923 Jamunipur 3 7 3314 2022 2037 2052 22-May-2023 13-Oct-2025 13-Oct-2025 14-Oct-2025 Checked and found ok. Okay View
5 Jaunpur Welspun Kaveri Infraprojects JV 20020928 Jarauta 3 3 2580 2022 2037 2052 22-May-2023 13-Oct-2025 13-Oct-2025 14-Oct-2025 Checked and found ok. Ok View
6 Jaunpur Welspun Kaveri Infraprojects JV 20099650 Lapari Scheme-2 1 5 5115 2022 2037 2052 19-Oct-2024 14-Jul-2025 14-Jul-2025 15-Jul-2025 cheked and found ok. ok View
7 Jaunpur Welspun Kaveri Infraprojects JV 20066479 NAGAHTI 5 20 5331 2022 2037 2052 26-Jul-2024 28-Feb-2025 28-Feb-2025 01-Mar-2025 Testing & Commissioning certificate, Road restoration, trial & run certificate and Final BOQ not signed by EE but TPIA checked and signed all document for further process. ok View
8 Jaunpur Welspun Kaveri Infraprojects JV 20011273 PAAKRI 1 3 2420 2022 2037 2052 23-Sep-2023 13-Oct-2025 13-Oct-2025 14-Oct-2025 Testing & Commissioning certificate, Road restoration, trial & run and Final BOQ not signed by EE but TPIA checked and signed all document for further process. ok View
9 Jaunpur Welspun Kaveri Infraprojects JV 20020896 Prempur 2 6 3490 2022 2037 2021 22-May-2023 31-Dec-2024 20-Dec-2024 21-Dec-2024 Checked & Found ok ok View
10 Jaunpur Welspun Kaveri Infraprojects JV 20016242 Rampur Ta Jakhaniyan 1 9 5328 2022 2037 2052 06-Jul-2023 28-Feb-2025 28-Feb-2025 01-Mar-2025 Checked and found ok. Ok View
11 Jaunpur Welspun Kaveri Infraprojects JV 20009954 SAMRAHO 1 8 3320 2022 2037 2052 22-May-2023 28-Feb-2025 28-Feb-2025 01-Mar-2025 Checked and found ok. Ok View
12 Jaunpur Welspun Kaveri Infraprojects JV 20022191 Sarai Bikram 1 10 5480 2022 2037 2052 06-Jul-2023 18-Oct-2025 18-Oct-2025 19-Oct-2025 Checked and found ok. Okay View
13 Jaunpur Welspun Kaveri Infraprojects JV 20011558 Sujiya Mau 4 20 5008 2022 2037 2052 23-Sep-2023 20-Jun-2025 20-Jun-2025 21-Jun-2025 Checked and found ok........... Ok View