Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in

Jal Jeevan Mission - District Dashboard  - Azamgarh

       
Heirarchy / District Progress Reference
Total Block :
Total Panchayat :
Total Villages :
Population :
Households :
FHTC :
FHTC(%) :
Total HGJ Villages:
Total Certified :
Handed Over Villages :
GP level member :
VWSC/ Pani Samiti/ Water User Group :
Operation and Maintenance User :
Women identified for field test kit (FTK) testing :
Skilled Human Resources available in village :
UP Jal Nigam Old Scheme
Total Scheme :
Total Village :
Total OHT :
Schemes send to O&M Details
Total Scheme :
Total Village :
Total OHT :
Water Demand Daily(M3):
Water Demand Weekly(M3):
Water Demand Monthly(M3):
Water Supply Daily(M3):
Water Supply Weekly(M3):
Water Supply Monthly(M3):
Partial Complete Schemes Details
Total Scheme :
Total Village :
Total OHT :
Water Demand Daily(M3):
Water Demand Weekly(M3):
Water Demand Monthly(M3):
Water Supply Daily(M3):
Water Supply Weekly(M3):
Water Supply Monthly(M3):
Incoming Complaints/Feedback Received
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Details(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
ISA Activities
Total ISA Activities :
Total Photos Uploaded :
Total Videos Uploaded :
IEC Activities
WorkShop/Wall Writing Activities :
PHASE II Activity :
IEC Regional Language Activity :
IEC Outdoor Activities :
Important Points for Review
DWSM MOM Date Subject DWSM MOM Attachment
07-Jan-2026 MOM of DWSM meeting month December 2025
Regular water supply disruption(Villages)
Theft :
Power/Electrical Issue :
Tullu Pump :
Road Widening :
Local Repairing :
Total OHT :
Automation Integration Status
Last 2 days Water Not Supply OHT(Disconnected OHT) :
Pending Complaints :
Department Contact Number
S.No. Name Designation Monile No.
1 Rajendra Kumar Executive Engineer 9473942706
2 Azamgarh DM 9454417521
3 Satya Prakash JE 8840312648
4 Ajay Kumar JE 6306594419
5 Pinku singh Chauhan JE 9450645426
6 Rajendra Kumar JE 8090829165
7 Abhimanyu Gupta JE 8355079020
8 AtikAnsari JE 7390840644
9 Swatantra rao JE 7210433907
10 Ravi Kumar Patel JE 8931074519
11 Abhishek kumar singh JE 9140284305
12 Vikas kushwaha JE 8948412290
13 ATIK ANSARI JE 7390840644
14 Manish Maurya JE 9451615067
15 Rajendra Kumar_ JE 8090829165
16 INDRASEN CHAKRABORTY JE 9628931574
17 Rajendra Kumar JE 8090829165
18 RAJSHEKAR JE 8753673733
19 Satyaprakash JE 8840312648
20 Vijay Pratap Yadav JE 9838941497
21 Deepak Yadav JE 8808782256
22 Ajay Kumar JE 6306594419
23 Azamgarh EE E AND M 9512113735
JJM Scheme Details Phase 1       Phase 2,3,5       Phase 4
Total JJM Scheme :
Total JJM Scheme Covered Village :
O&M Schemes
O&M Schemes:
O&M JJM Village :
O&M Schemes Integrate With Automation :
Automation Integrated Schemes
Automation Installed Scheme:
Integrated Scheme :
Integrated OHT :
Integrated Village :
Live Connected OHT :
Live Pump On OHT :
Last 2 days Water Not Supply OHT :
Regular Water Supply OHT :
Water supply less than 75% percent :
Water supply greater than 150% percent :
Automation Integrated Verified Schemes (EE E&M)
Integrated Scheme :
Integrated OHT :
Integrated Village :
Functional OHT Water Demand/Supply (Meter 3)
Water Demand Daily :
Water Demand Weekly :
Water Demand Monthly :
Water Supply Daily :
Water Supply Weekly :
Water Supply Monthly :
Automation Integrated SchemesReference
Sno. Scheme Status Pump Status Scheme Id Scheme Name Agency Name Covered Village Regular Water Supply Last Data Receive Date
Total 15 13
1 8388634 HARAKHPURA KHAS LC INFRA 1 1 15-04-2026 11:02 PM
2 20015114 Bhirbhanpur water supplyscheme LC INFRA 1 1 15-04-2026 10:44 PM
3 20015222 amrethoo water supply scheme LC INFRA 1 0 15-04-2026 11:01 PM
4 20015229 KASBA FATEHPUR WATE SUPPLY SCHEME LC INFRA 1 1 15-04-2026 10:44 PM
5 20015278 Chauki Baradah water supply scheme LC INFRA 1 0 15-04-2026 11:02 PM
6 20015455 Pawani kala water supply scheme LC INFRA 1 1 15-04-2026 11:01 PM
7 20021842 UKRAUDA WATER SUPPLY SCHEME GA INFRA - BABA (JV) 2 2 15-04-2026 10:44 PM
8 20049619 JAMUNWA SAGAR WATER SUPPLY SCHEME GA INFRA - BABA (JV) 4 4 15-04-2026 11:00 PM
9 20049988 TANDWA WATER SUPPLY SCHEME GA INFRA - BABA (JV) 2 2 15-04-2026 10:59 PM
10 20050027 DHOLIPUR WATER SUPPLY SCHEME GA INFRA - BABA (JV) 1 1 15-04-2026 10:57 PM
Components Wise Physical Progress
Sr.No. Components Target Achivement %
1 2 3 4 5
1 Tubewell 1500 1484 98.93
2 Pump House 1500 1452 96.80
3 Chlorination system 869 785 90.33
4 OHT 1459 1435/905 98.36
5 Distribution (Line Laying in Km.) 19353 18399 95.07
6 Solar Plant 1430 1148 80.28
7 F.H.T.C. 623970 591901 94.86
9 ROAD DISMENTLING/RESTORATION(KM) 7155 6977 97.51
10 Villages where 100 % road restoration completed 97070 60832 62.67
11 Comissioning of Village 3630 1684 46.39
12 Regular water supply 3630 1817 50.06
Agency Progress Details
Sr.No. Agency No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 ECO PROTECTION ENGINEER 111 344 47001 45521 96.85% 214 15
2 GA INFRA - BABA (JV) 128 303 69679 66513 95.46% 208 96
3 GAJA - SGIPL (JV) 121 389 45022 41167 91.44% 206 4
4 LC INFRA 402 856 174714 166907 95.53% 241 143
5 SIEPL – BRCCPL (JV) / SKYLARK 117 291 38927 37111 95.33% 121 39
6 M/s Sudhakara Infratech Pvt. Ltd 429 1145 170856 159860 93.56% 249 33
7 VIKRAN-VPRPL (JV) 152 302 49476 46631 94.25% 58 4
Total 1460 3630 595675 563710 94.63% 1297 334
DWSM Minutes of Meeting
S.No. DWSM MOM Date Subject Attachment
1 07-Jan-2026 MOM of DWSM meeting month December 2025
2 07-Nov-2025 DWSM meeting for month October2025
3 10-Oct-2025 DWSM meeting MOM for month September 2025
4 04-Sep-2025 Monthly proogress review meeting for August 2025
5 28-Jul-2025 A meeting was held with the agency in which the review of the pending schemes from the last 2 years and 3 years was conducted.
6 04-Jul-2025 A meeting was held with the agency in which the review of the pending schemes from the last 2 years and 3 years was conducted.
7 22-May-2025 The monthly progress reports of all agencies were reviewed.
8 07-Apr-2025 The monthly progress reports of all agencies were reviewed.