Sr.No. District Town Name of Sewerage Project Scheeme Type Mode of Project AA&ES and date No. of STP STP Capacity No.Of Drains Agency Name Agreement Cost
Date of Start
Date of Comp. As per Agreement
Revised Date
Current progress
Date of updation
Remark
Date of Sanction Sanction cost (In Cr.) work Cost (In Cr.) Centage (In Cr.) O & M Cost (In Cr.) Physical Progress Financial Progress
Total -- 5941.73 2667.74 192.10 3062.79 36 982.60 129 -- 4109.81 -- -- --
--
+ 4.29
940.31
-- --
1 Agra Agra Agra Sewerage Scheme( Interception & diversion and STP works) NGP2-EAP HAM 06-May-2020 842.25 371.29 25.40 445.56 13 177.60 26 M/s AWWMPL Pvt Ltd 582.84 05-Apr-2023 04-Apr-2025 04-Apr-2025 +0.52
58.06
+0.00
150.22
10-Feb-2025
  • Component wise progress of Agra (HAM) 100 MLD STP- 62.50%, WIP 35 MLD STP- 70%, WIP 31 MLD STP- 68%, WIP MPS 03 Nos.- 10%, WIP Rising Main 9.55 Km- 38.64%, WIP Gravity Sewer 2.55 Km- 80%, WIP DSTP 10 Nos.- 5%, WIP Note- 1st Stage permission is granted for 07 Nos. DSTP Forest Land and 2nd stage permission is under process
2 Ayodhya Faizabad Pollution Abatement Works for River Saryu/Ghaghara at Faizabad town, District-Ayodhya (Interception & Diversion of Drains with 33 MLD STP) NGP HAM 06-May-2021 221.66 109.03 7.62 105.01 1 33.00 15 M/s Eco Protection Engineer Pvt Ltd 149.47 03-Mar-2023 02-Jan-2025 30-Sep-2024,
31-Dec-2024,
31-May-2024
+0.02
96.90
+0.00
86.86
13-Feb-2025
  • NMCG has given NOC for discharge of treated effluent in Saryu River dated 19.08.2024. Subsequently, correspondence with all supporting documents has been given to Irrigation Department for NOC of crossing effluent line across Bundha.
  • Precommissioning of MPS, PTU, SBR basin, Diffuser, Blower, Disc filter has been completed.
3 Hapur Hapur I&D and STP works at District-Hapur NGP DBOT 19-Sep-2023 49.06 22.85 1.42 24.79 1 6.00 1 M/s SKC Technocrat Pvt. Ltd (Formerly M/s Satish Kumar & Co.) & M/s. Geo Miller & Co. Pvt. Ltd. (JV) 39.28 08-Nov-2024 07-Nov-2026 +1.00
8.00
+0.00
0.00
10-Feb-2025
  • Soil Testing and Boundary Wall work is in progress...
  • Date of start is given on 08.11.24. Date of completion of work is 05.02.2026 to M/s SKC Technocrat Pvt. Ltd (Formerly M/s Satish Kumar & Co.) & M/s. Geo Miller & Co. Pvt. Ltd. (JV), Reg. Office B-29, IIIrd Floor, RDC Rajnagar, Ghaziabad - 201013. AGREEMENT cost of project is Rs. 39,28,13,617.00.
4 Hathras Hathras I&D and STP works at Hathras Town NGP DBOT 30-Jan-2023 128.91 70.48 4.55 53.88 1 24.00 10 M/s Neercare India pvt KLtd JV M/s EMIT Group India Pvt Ltd JV EMS Ltd 119.05 06-Sep-2024 05-Jun-2026 05-Jun-2026 +0.00
0.00
+0.00
0.00
10-Feb-2025
  • Date of start is 06.09.2024 and date of completion is 05.06.2024. Survey work is going on.
  • Survey and soil investigation has been completed by firm
  • BEP is under preparation by firm
  • The project land is not yet available for any work because it is encroached by a vendor of palika parishad, for which continous communications has been estabilished to EO, Palika & disrict administration , but till date no outcome has been received.
5 Kanpur Nagar Kanpur Nagar I&D and STP works at Kanpur-Pankha NGP HAM 12-Mar-2018 967.23 248.39 31.05 718.84 1 30.00 2 M/s Kanpur River Management Pvt. Ltd. 708.70 11-Oct-2019 25-Oct-2021 29-Feb-2024,
30-Sep-2024,
31-Aug-2024,
31-Oct-2024
+0.00
99.00
+0.00
341.83
10-Feb-2025
6 Lucknow Pollution Abatement Of Gomti River (Phase 1 Part 1) Lucknow NGP DBOT 29-Jul-2024 240.93 123.45 6.97 110.51 1 3.50 1 M/s R.K. Engineers- Khilari Infrastructure (JV) 187.90 07-Sep-2024 06-Jun-2026 +1.19
3.06
+0.00
0.00
10-Feb-2025
  • Date of start of 3.5 MLD Barikala STP is given on dt. 07.09.2024 to M/s R.K. Engineers Sales Ltd. - Khilari Infrastructures (JV). Preparation of Design & Drawing of the project is in progress.
7 Lucknow Lucknow Pollution Abatement of Gomti River (Phase-II, Part-I) Lucknow NGP DBOT 30-Jan-2023 264.67 137.55 8.53 118.60 1 50.00 3 M/s R.K. Engineers- Khilari Infrastructure (JV) 187.74 14-Jun-2024 13-Mar-2026 +0.03
0.72
+0.00
0.00
10-Feb-2025
  • Date of start is given on dt. 14.06.2024 to M/s R.K. Engineers Sales Ltd. - Khilari Infrastructures (JV). Soil testing at STP site and construction of staff quarter is completed, Preparation of BEP of the project is in progress..
8 Mathura Chhata Chhata Town Sewerage Scheme (I&D and STP works), District Mathura NGP DBOT 25-Oct-2022 56.15 34.52 2.23 19.40 1 6.00 14 M/s Shailesh Kumar J.V. 48.97 12-Nov-2024 11-Aug-2026 +0.10
0.85
+0.00
0.00
10-Feb-2025
  • Date of Start 12.11.2024 has been given to the firm. Survey and other related works is going on.
  • BEP is under submission by firm
  • Survey and soil investigation has been done by firm.
9 Mathura Vrindavan I&D and 13 MLD STP works at Vrindavan City NGP DBOT 25-Oct-2022 77.70 39.90 2.56 35.24 1 13.00 2 M/s SIMA -G D- N.P. (JV) 65.86 11-Jun-2024 10-Mar-2026 +0.07
27.31
+0.00
3.39
10-Feb-2025
  • LOA issued to firm on dated 15.03.2024. Effective Date of start for the work is 11.06.2024.Work is in progress.
10 Mathura Kosi Kalan I&D and STP works at Kosi Kalan Town, District Mathura NGP DBOT 25-Oct-2022 66.59 31.24 2.03 33.32 1 12.00 1 M/s R K Engineers Sales Ltd 53.60 16-Oct-2024 15-Jul-2026 +0.00
0.00
+0.00
0.00
10-Feb-2025
  • LOA has been issued on date 18.06.2024 and Date of start has been given 16.10.2024 to the firm. Survey work is going on
  • Survey and soil investigation has been done by firm.
  • BEP documentation work of STP is in progress by firm
  • Continous instruction has been given to firm for expediting the work.
11 Mathura Mathura Mathura sewerage scheme (I&D and STP Works for balance drain) NGP2-NON EAP HAM 07-Sep-2022 292.56 149.85 9.61 133.10 1 60.00 4 M/s EIEL Mathura Infra Engineers Private Limited 240.01 30-Nov-2024 29-Nov-2026 +4.63
14.63
+0.00
19.40
10-Feb-2025
  • LOA issued to L1 Bidder on on 27.09.2023. CA signed on 12.12.2023. Effective date of start shall be to concessionaire after financial closure.
  • Effective date of start has been given to concessionaire as 30.11.2024.
  • IPS Kala Patthar and Rising main work is in progress
12 Meerut Meerut I&D and STP works at Meerut NGP2-EAP HAM 06-May-2020 690.71 363.78 26.31 280.19 1 220.00 2 M/s. Meerut STP Pvt. Ltd. 369.74 11-Nov-2024 10-Nov-2026 +1.00
14.00
+0.00
0.00
10-Feb-2025
  • Consent to Establishment from Pollution Control Board received. Basic Engineering Package, Admin, Tonner, SBR Basin, CCT design & Drawing Approved. BEP of I&D work Approved. Admin Building= 85%, Tonner Building= 75%, CCT= 60% SBR Basin= 9 Basin PCC work & 3 Basin Raft Concrete completed.
13 Moradabad Moradabad Interception & Diversion (I&D) of Drains and Sewerage Treatment Plant at Moradabad zone 2 NGP HAM 23-Jul-2018 118.69 53.53 3.52 61.64 1 25.00 5 Moradabad STP Pvt Ltd 113.85 20-Jan-2023 19-Jan-2025 19-Jan-2025 +0.00
86.00
+0.00
54.19
11-Feb-2025
  • 03 milestones have been completed and 86% progress is achieved of project
  • SBR progress is 85% and sewer has been laid 5457 m out of 6632
14 Muzaffarnagar Muzzaffarnagar I&D and STP Work in Muzaffarnagar NGP HAM 13-Jan-2020 234.03 108.32 7.33 118.36 2 54.50 5 M/S Muzaffarnagar STP Pvt Ltd 205.09 04-Jun-2021 03-Jun-2023 30-Jun-2024,
30-Sep-2024,
31-Mar-2025
+0.00
95.70
+0.00
141.79
10-Feb-2025
  • 22 MLD STP Sahawali: Commercial Operation Date declared, Plant under O&M since 01.04.2024.
  • 32.5 MLD Kidwai Nagar: 02 Nos. I&D work completed, STP running by 02 I&D. IPS 2A work in progress.
15 PrayagRaj Prayagraj Interception, Diversion of Balance 13 drains and Augmentation of Salori STP capacity by 43 MLD (Sewerage District-C) at Prayagraj Uttar Pradesh under DBOT mode NGP DBOT 14-Mar-2023 331.75 180.27 11.22 140.27 1 43.00 13 M/s HNB Private ltd. - M/s Tirupati Cements Products (JV) 204.40 19-Mar-2024 18-Aug-2025 +0.09
45.80
+0.00
22.74
13-Feb-2025
  • Basic Engineering Package has been vetted by IIT Delhi and same approved by UPJN (R)
  • GAD & RCC Design and Drawings of CCT, SBR Unit and Amitabh Bachhan Culvert SPS has been vetted by IIT Delhi and approved by UPJN (R)
  • RCC work for Raft is completed and wall of SBR unit of STP is under progress
  • Column Casting work is under progress for Air Blower ,Chlorine Tonner & MCC Room
  • Outer wall of SBR all unit of STP is completed and partian wall is under progress.
  • Casting of CCT Unit of STP is completed.
  • Casting of 6th Lift of Wall at AB Culvert SPS has been completed. Balance work is under progress.
  • 2050 m laying of Rising main completed. Balance Laying will be done after Mahakumbh -2025.
  • TEPS wall Casting work is Completed.
  • Piling and Pile Cap work for Sludge Dewatering Unit is under progress.
16 PrayagRaj Prayagraj Interception, Diversion of Balance 7 drains and Augmentation of Rajapur STP capacity by 90 MLD (Sewerage District-D) at Prayagraj Uttar Pradesh under DBOT mode NGP DBOT 27-Jan-2023 475.98 242.85 15.24 217.89 1 90.00 7 M/s Triveni Engineering and Industries 309.74 24-Aug-2024 23-Feb-2026 +1.00
11.00
+0.00
20.30
10-Feb-2025
  • 2200 m laying of Rising main completed. Balance Laying is under progress.
  • Supply of 1000 DI K-9 Pipe for rising main is in progress.
  • BEP has been approved.
  • Excavation of SBR is in progress.
  • Contract Agreement has been executed.
  • Date of Start 24.08.2024 and Date of Completion 23.02.2026 including 3 month of Trial and run has been given to the firm M/s Triveni Engineering and Industries Limited.
  • Survey, Design and Drawing work is in progress
17 Shamli Banat I&D and STP Work in Banat, Shamli NGP DBOT 25-May-2023 48.71 24.93 1.58 22.20 1 5.00 3 M/s R K Engineers Sales Ltd 37.92 14-Oct-2024 13-Jan-2026 +0.00
5.00
+0.00
0.00
10-Feb-2025
  • Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
  • Survey and Soil investigation work completed, BEP Submitted on dated 27.12.2024 but return with comments on same day.
18 Shamli Bantikhera Banat I&D and STP Work in Bantikhera and Babri village, Shamli NGP DBOT 25-May-2023 55.47 29.41 1.84 24.22 1 5.00 1 M/s R K Engineers Sales Ltd 41.91 14-Oct-2024 13-Jan-2026 +0.00
5.00
+0.00
0.00
10-Feb-2025
  • Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
  • Survey and Soil investigation work completed, BEP Submitted on dated 27.12.2024 but return with comments on same day.
19 Shamli Shamli I&D and STP Work in Shamli NGP DBOT 25-May-2023 206.02 103.19 6.66 96.17 1 40.00 1 M/s R.K. Engineers Sales Ltd.-M/s Anand Constrwell Pvt. Ldt. (JV) 120.92 14-Oct-2024 13-Jan-2026 +0.00
5.00
+0.00
0.00
10-Feb-2025
  • Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
  • BEP submitted on dated 18.01.2025
  • Structured design is under process and it is to be submitted by the contractor at the end of month
  • Approach Road work in progress
20 Shamli Thanabhawan I&D and STP Work in Thanabhawan, Shamli NGP DBOT 25-May-2023 97.19 55.63 3.50 38.06 1 10.00 5 M/s R K Engineers Sales Ltd 63.72 14-Oct-2024 13-Jan-2026 +0.00
5.00
+0.00
0.00
10-Feb-2025
  • Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
  • Survey and Soil investigation work completed, BEP Submitted on dated 27.12.2024 but return with comments on same day.
  • Approach Road work in progress
21 Unnao Shuklaganj I&D of Drains and STP works in Shuklaganj (05MLD) NGP HAM 28-Jul-2017 65.18 25.93 1.90 37.35 1 5.00 5 M/s KRMPL Kanpur 38.87 11-Oct-2019 10-Jul-2021 10-Jul-2021,
13-Jun-2023,
14-Dec-2022,
30-Apr-2025,
31-Aug-2024,
31-Jan-2025
+0.00
81.50
+0.00
23.47
10-Feb-2025
  • There are only 57 manpower engaged in different Structure PTU, Admin Building, Air Blower, & Boundary wall work and only 6-8 manpower engaged in Electrical & Mechanical work Progress. . Most of the mechanical item reached at site but KRMPL has no planning for doing E&M works
22 Unnao Unnao I&D of Drains and STP works in Unnao (15MLD) NGP HAM 28-Jul-2017 102.20 43.73 3.22 55.25 1 15.00 1 M/s KRMPL Kanpur 68.68 11-Oct-2019 10-Jul-2021 10-Jul-2021,
15-Mar-2023,
15-Oct-2022,
15-Sep-2021,
25-Feb-2022,
30-Apr-2023,
30-Jun-2024,
31-Dec-2024,
31-Jul-2024,
31-Mar-2025
+0.00
96.10
+0.00
52.01
10-Feb-2025
  • Dewatering & Cleaning of 423 meter work in progress and new pipe laying of 52.50 meter pipe laying out of 400 meter sewer line is done balance work in progress KRMPL deployed total 62 manpower at site out of which cleaning of Sewer line 38 manpower & new pipe laying 24 manpower. STP 24 Hrs operating daily from 11.1.2025 through temporary line but CCT is not functional till date due to commissioning of CCT WORK IS PENDING from KRMPL also material short fall PAD HEATER & Pressure switch.
23 Varanasi Varanasi I&D and Treatment works for Assi-BHU Area (Phase-II), Varanasi NGP DBOT 19-Oct-2022 308.09 97.62 7.81 172.94 1 55.00 2 M/s Enviro Infra Engineers limited MTS JV 151.55 07-Mar-2024 06-Dec-2025 +1.00
33.00
+4.29
24.11
13-Feb-2025
  • BEP submitted by firm to which observation have been raised. compliance pending.
  • Soil testing done. Team mobilized at site.
  • Meeting held under chairmanship of APD Sir on 20.06.2024 to resolve issues of design/drawing. Firm submitted BEP of STP only on 24.06.2024
  • Vetting of process flow of STP and MPS done by IIT-BHU. Structural drawing awaited. Preparatory works in progress