Sr.No. District Town Name of Sewerage Project Scheeme Type Mode of Project AA&ES and date No. of STP STP Capacity No.Of Drains Agency Name Agreement Cost
Date of Start
Date of Comp. As per Agreement
Revised Date
Current progress
Date of updation
Remark
Date of Sanction Sanction cost (In Cr.) work Cost (In Cr.) Centage (In Cr.) O & M Cost (In Cr.) Physical Progress Financial Progress
Total -- 4640.20 1983.76 145.56 2516.09 35 707.30 146 -- 3489.82 -- -- --
--
+ 0.00
1396.74
-- --
1 Agra Agra Agra Sewerage Scheme( Interception & diversion and STP works) NGP2-EAP HAM 06-May-2020 842.25 371.29 25.40 445.56 13 177.60 26 M/s AWWMPL Pvt Ltd 582.84 05-Apr-2023 04-Apr-2025 04-Apr-2025 +0.52
45.02
+0.00
150.22
15-Jul-2024
  • Component wise progress of Agra (HAM) 100 MLD STP- 62.50%, WIP 35 MLD STP- 70%, WIP 31 MLD STP- 68%, WIP MPS 03 Nos.- 10%, WIP Rising Main 9.55 Km- 38.64%, WIP Gravity Sewer 2.55 Km- 80%, WIP DSTP 10 Nos.- 5%, WIP Note- 1st Stage permission is granted for 07 Nos. DSTP Forest Land and 2nd stage permission is under process
2 Ayodhya Faizabad Pollution Abatement Works for River Saryu/Ghaghara at Faizabad town, District-Ayodhya (Interception & Diversion of Drains with 33 MLD STP) NGP HAM 06-May-2021 221.66 109.03 7.62 105.01 1 33.00 15 M/s Eco Protection Engineer Pvt Ltd 149.47 03-Mar-2023 02-Jan-2025 30-Sep-2024,
31-May-2024
+0.48
91.76
+0.00
76.75
16-Jul-2024
  • Issue of disposal of Treated effluent at upstream .DGC meeting held on 15.05.24. MoM to be sent to SGC/NMCG for further approval.
  • All 4 SBR unit has been hydro-tested and air pipeline is completed. E&M work and pre-commissioning of Mechanical equipment is under progress. Finishing and land scaping work is in progress.
3 Bareilly Bareilly Development of Sewage Treatment Plant at Bareilly NGP HAM 03-Jan-2019 271.39 139.44 10.70 121.25 3 63.00 15 M/s EIEPL Bareilly Infra Engineers Ltd 233.72 31-Aug-2022 30-Aug-2024 30-Aug-2024 +0.00
99.00
+0.00
207.32
19-Jun-2024
4 Farrukhabad Farrukhabad-Fatehgarh I&D and STP works at Farrukhabad-Fatehgarh NGP HAM 09-Feb-2021 261.12 188.71 6.98 72.41 2 47.70 8 M/S HNB Engineers Private Ltd. 252.41 28-Jun-2022 27-Jun-2024 27-Jun-2024 +0.50
92.30
+0.00
179.04
15-Jul-2024
  • Construction of STP has been completed. Electro Mechanical works of STP and associated I and D works is in progress.
5 Ghazipur Ghazipur Sewerage, Sewage Treatment & Disposal for Ghazipur, U.P. NGP HAM 06-May-2020 152.83 50.96 4.08 96.17 1 21.00 23 M/s Mirzapur Ghazipur STPs Private Limited 140.94 10-Apr-2022 09-Jan-2024 31-Jul-2024 +0.00
99.50
+0.00
67.74
16-Jul-2024
  • STP has been commissioned.
  • Proposal of Additional cost implication approved by NMCG in EC meeting dt 13.02.2024. Work of TEPS and retaining wall is in progress and targeted to complete by July-24
6 Kanpur Nagar Kanpur Nagar I&D and STP works at Kanpur-Pankha NGP HAM 12-Mar-2018 967.23 248.39 31.05 718.84 1 30.00 2 M/s Kanpur River Management Pvt. Ltd. 708.70 11-Oct-2019 25-Oct-2021 29-Feb-2024,
31-Aug-2024
+0.00
99.00
+0.00
254.98
15-Jul-2024
  • 30 MLD Panka STP has been commissioned. Works of Sludge handling Unit and OCEMS are to be completed.
7 Lucknow Lucknow Pollution Abatement Of Gomti River (Phase 1 Part 1) Lucknow NGP DBOT 06-May-2020 213.91 101.31 6.97 105.63 2 42.50 2 M/s R.K. Engineers- Khilari Infrastructure (JV) 174.93 01-Jun-2022 30-Nov-2023 31-Jul-2024,
31-May-2024
+0.18
93.68
+0.00
94.86
15-Jul-2024
  • Work of 39 MLD Daulatganj STP is in progress. Principal approval of 3.5 MLD Barikala STP has been given by NMCG on dt. 09.06.2023 but financial approval for same is still awaited.
8 Lucknow Lucknow Pollution Abatement of Gomti River (Phase-II, Part-I) Lucknow NGP DBOT 30-Jan-2023 264.67 137.55 8.53 118.60 1 50.00 3 M/s R.K. Engineers- Khilari Infrastructure (JV) 187.74 14-Jun-2024 13-Dec-2025 +0.00
0.00
+0.00
0.00
01-Jul-2024
  • Design build starting date (14.06.2024) has been given to firm M/s R.K. Engineers - Khilari Infrastructures (JV)
9 Mathura Vrindavan I&D and 13 MLD STP works at Vrindavan City NGP DBOT 25-Oct-2022 77.70 39.90 2.56 35.24 1 13.00 2 M/s SIMA -G D- N.P. (JV) 65.86 11-Jun-2024 10-Mar-2026 +0.27
0.62
+0.00
0.00
15-Jul-2024
  • LOA issued to firm on dated 15.03.2024. Effective Date of start for the work is 11.06.2024.Work in progress.
10 Mirzapur Mirzapur Interception & Diversion and STP at Mirzapur, U.P. NGP HAM 28-May-2020 129.08 50.50 4.04 73.06 2 17.00 18 M/s Mirzapur Ghazipur STPs Private Limited 151.58 10-Apr-2022 09-Jan-2024 31-May-2024 +0.00
99.50
+0.00
74.36
16-Jul-2024
  • Temporary arrangement for discharge of treated effluent into existing channel completed.
  • Permission for discharge of treated effluent yet to be obtained. DGC denied recommendation for discharge in irrigation canal. Now location for discharge is identified 02 KM downstream of canal into Khajuri River for which draft variation proposal was sent to NMCG. In meeting dt 07.06.2024 under chairmanship of ED(P) NMCG it is directed to send the variation proposal through UPJN(HQ)/SMCG for approval which is submitted to CE(Ganga) on 14.06.2024
11 Moradabad Moradabad Interception & Diversion (I&D) of Drains and Sewerage Treatment Plant at Moradabad zone 2 NGP HAM 23-Jul-2018 118.69 53.53 3.52 61.64 1 25.00 5 Moradabad STP Pvt Ltd 113.85 20-Jan-2023 19-Jan-2025 19-Jan-2025 +0.50
69.50
+0.00
35.56
15-Jul-2024
  • 02 milestones have been completed and more than 69.5% progress is achieved of 3rd milestone.
  • SBR progress is 85% and sewer has been laid 4669 m out of 6632
12 Muzaffarnagar Muzzaffarnagar I&D and STP Work in Muzaffarnagar NGP HAM 13-Jan-2020 234.03 108.32 7.33 118.36 2 54.50 5 M/S Muzaffarnagar STP Pvt Ltd 205.09 04-Jun-2021 03-Jun-2023 30-Jun-2024,
30-Sep-2024
+1.07
95.16
+0.00
141.79
15-Jul-2024
  • 22 MLD STP Sahawali: Commissioned on 07.06.2023. Project completed on Oct, 2023
  • 32.5 MLD Kidwai Nagar: 02 Nos. I&D work completed, STP commissioned by Manual Mode by one I&D on dated 18 February, 2024. E&M Instrument installation work and finishing work in progress.
13 PrayagRaj Prayagraj Interception, Diversion of Balance 13 drains and Augmentation of Salori STP capacity by 43 MLD (Sewerage District-C) at Prayagraj Uttar Pradesh under DBOT mode NGP DBOT 14-Mar-2023 331.75 180.27 11.22 140.27 1 43.00 13 M/s HNB Private ltd. - M/s Tirupati Cements Products (JV) 204.40 19-Mar-2024 18-Aug-2025 +0.00
6.00
+0.00
4.74
19-Jun-2024
  • BEP has been submitted by firm on 9.5.2024. under review by IIT Delhi/UPJN
  • Observations from IIT Delhi/UPJN communicated to the firm on dated 27.05.2024.
  • Batching plant is installed, design mix has been provided by IIT, BHU and excavation work of CCT, SBR is under progress.
14 Shamli Kairana I&D and STP Work in Kairana NGP DBOT 07-Dec-2020 78.42 37.28 2.63 38.51 1 15.00 1 M/s SIPL RKC JV 59.19 28-Aug-2021 27-May-2023 30-Jun-2024,
31-Aug-2024
+0.29
96.09
+0.00
29.58
15-Jul-2024
  • STP has been commissioned on 12.2.2024
  • Minor finishing, road and draingae works under progress
15 Unnao Shuklaganj I&D of Drains and STP works in Shuklaganj (05MLD) NGP HAM 28-Jul-2017 65.18 25.93 1.90 37.35 1 5.00 5 M/s KRMPL Kanpur 38.87 11-Oct-2019 10-Jul-2021 10-Jul-2021,
13-Jun-2023,
14-Dec-2022,
31-Aug-2024
+0.00
81.00
+0.00
23.47
15-Jul-2024
  • There are only 10-20 manpower has been engaged in centrifuge. Manhole PTU and I&D work No any manpower deployed in Electrical & Mechanical works from last 8-10 months. Progress of work is very poor.
16 Unnao Unnao I&D of Drains and STP works in Unnao (15MLD) NGP HAM 28-Jul-2017 102.20 43.73 3.22 55.25 1 15.00 1 M/s KRMPL Kanpur 68.68 11-Oct-2019 10-Jul-2021 10-Jul-2021,
15-Mar-2023,
15-Oct-2022,
15-Sep-2021,
25-Feb-2022,
30-Apr-2023,
30-Jun-2024,
31-Jul-2024
+0.00
95.50
+0.00
52.01
15-Jul-2024
  • Cleaning of 315mt. sewer line is balance till date and From last one week KRMPL not deployed manpower at site for cleaning of Sewer line. STP 4-6 Hrs operating daily from 07.11.2023 through temporary line.
17 Varanasi Varanasi I&D and Treatment works for Assi-BHU Area (Phase-II), Varanasi NGP DBOT 19-Oct-2022 308.09 97.62 7.81 172.94 1 55.00 2 M/s Enviro Infra Engineers limited MTS JV 151.55 07-Mar-2024 06-Dec-2025 +0.00
3.00
+0.00
4.32
16-Jul-2024
  • BEP submitted by firm to which observation have been raised. compliance pending.
  • Soil testing done. Team mobilized at site.
  • Meeting held under chairmanship of APD Sir on 20.06.2024 to resolve issues of design/drawing. Firm submitted BEP of STP only on 24.06.2024