Sr.No. District Town Name of Sewerage Project Scheeme Type Mode of Project AA&ES and date No. of STP STP Capacity No.Of Drains Agency Name Agreement Cost
Date of Start
Date of Comp. As per Agreement
Revised Date
Current progress
Date of updation
Remark
Date of Sanction Sanction cost (In Cr.) work Cost (In Cr.) Centage (In Cr.) O & M Cost (In Cr.) Physical Progress Financial Progress
Total -- 4613.37 2018.91 143.90 2458.87 30 705.30 106 -- 3333.18 -- -- --
--
+ 7.12
1088.56
-- --
1 Agra Agra Agra Sewerage Scheme( Interception & diversion and STP works) NGP2-EAP HAM 06-May-2020 842.25 371.29 25.40 445.56 13 177.60 26 M/s AWWMPL Pvt Ltd 582.84 05-Apr-2023 04-Apr-2025 04-Apr-2025 +0.44
49.80
+0.00
150.22
07-Oct-2024
  • Component wise progress of Agra (HAM) 100 MLD STP- 62.50%, WIP 35 MLD STP- 70%, WIP 31 MLD STP- 68%, WIP MPS 03 Nos.- 10%, WIP Rising Main 9.55 Km- 38.64%, WIP Gravity Sewer 2.55 Km- 80%, WIP DSTP 10 Nos.- 5%, WIP Note- 1st Stage permission is granted for 07 Nos. DSTP Forest Land and 2nd stage permission is under process
2 Ayodhya Faizabad Pollution Abatement Works for River Saryu/Ghaghara at Faizabad town, District-Ayodhya (Interception & Diversion of Drains with 33 MLD STP) NGP HAM 06-May-2021 221.66 109.03 7.62 105.01 1 33.00 15 M/s Eco Protection Engineer Pvt Ltd 149.47 03-Mar-2023 02-Jan-2025 30-Sep-2024,
31-Dec-2024,
31-May-2024
+0.77
95.56
+0.00
76.75
07-Oct-2024
  • NMCG has given NOC for discharge of treated effluent in Saryu River dated 19.08.2024. Subsequently, correspondence with all supporting documents has been given to Irrigation Department for NOC of crossing effluent line across Bundha.
  • Precommissioning of MPS, PTU, SBR basin, Diffuser, Blower, Disc filter has been completed.
3 Farrukhabad Farrukhabad-Fatehgarh I&D and STP works at Farrukhabad-Fatehgarh NGP HAM 09-Feb-2021 261.12 188.71 6.98 72.41 2 47.70 8 M/S HNB Engineers Private Ltd. 252.41 28-Jun-2022 27-Jun-2024 27-Jun-2024,
30-Sep-2024,
31-Aug-2024,
31-Oct-2024
+0.20
94.70
+0.00
179.04
07-Oct-2024
  • Construction of STP has been completed. Electrical and Mechanical works of STP and associated I and D works are in progress. The power connection is to be provided by concerning department UPPCL. The power connection work under progress.
4 Hathras Hathras I&D and STP works at Hathras Town NGP DBOT 30-Jan-2023 128.91 70.48 4.55 53.88 1 24.00 10 M/s Neercare India pvt KLtd JV M/s EMIT Group India Pvt Ltd JV EMS Ltd 119.05 05-Jun-2026 06-Sep-2024 05-Jun-2026 +0.00
0.00
+0.00
0.00
  • Date of start is 06.09.2024 and date of completion is 05.06.2024. Survey work is going on
5 Kanpur Nagar Kanpur Nagar I&D and STP works at Kanpur-Pankha NGP HAM 12-Mar-2018 967.23 248.39 31.05 718.84 1 30.00 2 M/s Kanpur River Management Pvt. Ltd. 708.70 11-Oct-2019 25-Oct-2021 29-Feb-2024,
30-Sep-2024,
31-Aug-2024,
31-Oct-2024
+0.00
99.00
+0.00
298.00
07-Oct-2024
  • 30 MLD Panka STP has been commissioned. Works of Sludge handling Unit has been completed. OCEMS has been installed but not functional.
6 Lucknow Lucknow Pollution Abatement Of Gomti River (Phase 1 Part 1) Lucknow NGP DBOT 06-May-2020 213.91 101.31 6.97 105.63 2 42.50 2 M/s R.K. Engineers- Khilari Infrastructure (JV) 174.93 01-Jun-2022 30-Nov-2023 31-Jul-2024,
31-May-2024
+0.00
96.63
+0.00
94.86
07-Oct-2024
  • Works of 39MLD STP has been completed.
  • Revised AA&ES for 3.5 MLD Barikala STP has been issued by NMCG on dt. 29.07.2024.
7 Lucknow Lucknow Pollution Abatement of Gomti River (Phase-II, Part-I) Lucknow NGP DBOT 30-Jan-2023 264.67 137.55 8.53 118.60 1 50.00 3 M/s R.K. Engineers- Khilari Infrastructure (JV) 187.74 14-Jun-2024 13-Dec-2025 +0.00
0.00
+0.00
0.00
07-Oct-2024
  • Date of start is given on date 14.06.2024 to M/s R.K. Engineer sales ltd.- Khliari Infrastructures (JV). Construction of Staff Quarter is in progress.
8 Mathura Vrindavan I&D and 13 MLD STP works at Vrindavan City NGP DBOT 25-Oct-2022 77.70 39.90 2.56 35.24 1 13.00 2 M/s SIMA -G D- N.P. (JV) 65.86 11-Jun-2024 10-Mar-2026 +0.10
3.50
+0.00
0.00
07-Oct-2024
  • LOA issued to firm on dated 15.03.2024. Effective Date of start for the work is 11.06.2024.Work in progress.
9 Moradabad Moradabad Interception & Diversion (I&D) of Drains and Sewerage Treatment Plant at Moradabad zone 2 NGP HAM 23-Jul-2018 118.69 53.53 3.52 61.64 1 25.00 5 Moradabad STP Pvt Ltd 113.85 20-Jan-2023 19-Jan-2025 19-Jan-2025 +0.50
77.50
+0.00
35.56
08-Oct-2024
  • SBR progress is 85% and sewer has been laid 4669 m out of 6632
  • 02 milestones have been completed and more than 77.5% progress is achieved of 3rd milestone.
10 Muzaffarnagar Muzzaffarnagar I&D and STP Work in Muzaffarnagar NGP HAM 13-Jan-2020 234.03 108.32 7.33 118.36 2 54.50 5 M/S Muzaffarnagar STP Pvt Ltd 205.09 04-Jun-2021 03-Jun-2023 30-Jun-2024,
30-Sep-2024
+0.00
95.68
+0.00
141.79
03-Oct-2024
  • 22 MLD STP Sahawali: Commissioned on 07.06.2023. Project completed on Oct, 2023
  • 32.5 MLD Kidwai Nagar: 02 Nos. I&D work completed, STP commissioned by Manual Mode by 02 I&D on dated 18 February, 2024. IPS 2A work in progress.
11 PrayagRaj Prayagraj Interception, Diversion of Balance 13 drains and Augmentation of Salori STP capacity by 43 MLD (Sewerage District-C) at Prayagraj Uttar Pradesh under DBOT mode NGP DBOT 14-Mar-2023 331.75 180.27 11.22 140.27 1 43.00 13 M/s HNB Private ltd. - M/s Tirupati Cements Products (JV) 204.40 19-Mar-2024 18-Aug-2025 +0.00
18.00
+0.00
21.10
04-Oct-2024
  • Basic Engineering Package has been vetted by IIT Delhi and same approved by UPJN (R)
  • GAD & RCC Design and Drawings of CCT, SBR Unit and Amitabh Bachhan Culvert SPS has been vetted by IIT Delhi and approved by UPJN (R)
  • 660 m Laying of Rising Main of 1000 mm dia DI K-9 pipe from Amitabh Bachhan Culvert SPS to 43 MLD Salori STP has been completed
  • 3rd Lift of Amitabh Bachhan Culvert SPS wall has been completed. Steel Binding is in progress.
  • Reinforcement work for wall of CCT Unit of STP has been completed and RCC Casting work for the same is under progress
  • Reinforcement and Concreting work for raft of SBR is under progress
12 PrayagRaj Prayagraj Interception, Diversion of Balance 7 drains and Augmentation of Rajapur STP capacity by 90 MLD (Sewerage District-D) at Prayagraj Uttar Pradesh under DBOT mode NGP DBOT 27-Jan-2023 475.98 242.85 15.24 217.89 1 90.00 7 M/s Triveni Engineering and Industries 309.74 24-Aug-2024 23-Feb-2026 +1.00
1.00
+7.12
7.12
04-Oct-2024
  • Date of Start 24.08.2024 and Date of Completion 23.02.2026 including 3 month of Trial and run has been given to the firm M/s Triveni Engineering and Industries Limited.
  • NMCG, New Delhi has given consent on dated 02.08.2024 regarding approval of financial bid.
  • Letter of Award (LOA) has been issued to the firm on dated 09.08.2024
  • Contract Agreement has been executed.
  • Survey, Design and Drawing work is in progress
13 Unnao Shuklaganj I&D of Drains and STP works in Shuklaganj (05MLD) NGP HAM 28-Jul-2017 65.18 25.93 1.90 37.35 1 5.00 5 M/s KRMPL Kanpur 38.87 11-Oct-2019 10-Jul-2021 10-Jul-2021,
13-Jun-2023,
14-Dec-2022,
31-Aug-2024,
31-Jan-2025
+0.00
81.00
+0.00
23.47
07-Oct-2024
  • There are only 10-20 manpower has been engaged in centrifuge. Manhole PTU and I&D work No any manpower deployed in Electrical & Mechanical works from last 8-10 months. Progress of work is very poor.
14 Unnao Unnao I&D of Drains and STP works in Unnao (15MLD) NGP HAM 28-Jul-2017 102.20 43.73 3.22 55.25 1 15.00 1 M/s KRMPL Kanpur 68.68 11-Oct-2019 10-Jul-2021 10-Jul-2021,
15-Mar-2023,
15-Oct-2022,
15-Sep-2021,
25-Feb-2022,
30-Apr-2023,
30-Jun-2024,
31-Dec-2024,
31-Jul-2024
+0.00
95.50
+0.00
52.01
07-Oct-2024
  • Cleaning of 423mt. sewer line is balance till date and From last 2-3month KRMPL not deployed manpower at site for cleaning of Sewer line. STP 4-6 Hrs operating daily from 07.11.2023 through temporary line.
15 Varanasi Varanasi I&D and Treatment works for Assi-BHU Area (Phase-II), Varanasi NGP DBOT 19-Oct-2022 308.09 97.62 7.81 172.94 1 55.00 2 M/s Enviro Infra Engineers limited MTS JV 151.55 07-Mar-2024 06-Dec-2025 +0.00
14.00
+0.00
8.64
30-Sep-2024
  • BEP submitted by firm to which observation have been raised. compliance pending.
  • Soil testing done. Team mobilized at site.
  • Meeting held under chairmanship of APD Sir on 20.06.2024 to resolve issues of design/drawing. Firm submitted BEP of STP only on 24.06.2024
  • Vetting of process flow of STP and MPS done by IIT-BHU. Structural drawing awaited. Preparatory works in progress