Physical Progress Phase-2, 3 & 5 |
||||
---|---|---|---|---|
Sr.No. | Components | Taget | Achivement | % |
1 | 2 | 3 | 4 | 5 |
1 | Tubewell | 38355 | 37864 | 98.72 |
2 | Pump House | 38355 | 36557 | 95.31 |
3 | OHT | 36393 | 35703/10644 | 98.10 |
4 | Distribution (Line Laying in Km.) | 419232 | 419232 | 100.00 |
5 | Solar Plant | 32806 | 27733 | 84.54 |
6 | HGJ Status | 72136 | 27605 | 38.27 |
7 | Comissioning of Village | 72136 | 36226 | 50.22 |
8 | ROAD DISMENTLING/RESTORATION(KM) | 174148 | 168718 | 96.88 |