Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in

Components Wise Physical Progress

Physical Progress Phase-2, 3 & 5

Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 38388 37988 98.96
2 Pump House 38388 37238 97.00
3 OHT 36457 35519/18107 97.43
4 Distribution (Line Laying in Km.) 450579 425509 94.44
5 Solar Plant 32871 28949 88.07
6 HGJ Status 72905 36667 50.29
7 Comissioning of Village 72905 44986 61.70
8 ROAD DISMENTLING/RESTORATION(KM) 181013 176459 97.48