Physical Progress Phase-2, 3 & 5 |
||||
|---|---|---|---|---|
| Sr.No. | Components | Taget | Achivement | % |
| 1 | 2 | 3 | 4 | 5 |
| 1 | Tubewell | 38387 | 37990 | 98.97 |
| 2 | Pump House | 38387 | 37218 | 96.95 |
| 3 | OHT | 36442 | 35525/19179 | 97.48 |
| 4 | Distribution (Line Laying in Km.) | 450526 | 425962 | 94.55 |
| 5 | Solar Plant | 32863 | 29026 | 88.32 |
| 6 | HGJ Status | 72795 | 37754 | 51.86 |
| 7 | Comissioning of Village | 72795 | 46604 | 64.02 |
| 8 | ROAD DISMENTLING/RESTORATION(KM) | 181784 | 177111 | 97.43 |