Components Wise Physical Progress

Physical Progress Phase-2, 3 & 5

Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 38386 38006 99.01
2 Pump House 38386 37275 97.11
3 OHT 36444 35841/20809 98.35
4 Distribution (Line Laying in Km.) 450569 426581 94.68
5 Solar Plant 32837 29144 88.75
6 HGJ Status 72776 40506 55.66
7 Comissioning of Village 72776 47214 64.88
8 ROAD DISMENTLING/RESTORATION(KM) 192431 185941 96.63