Components Wise Physical Progress

Physical Progress Phase-2, 3 & 5

Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 38355 37853 98.69
2 Pump House 38355 36466 95.07
3 OHT 36390 35697/10016 98.10
4 Distribution (Line Laying in Km.) 417826 417826 100.00
5 Solar Plant 32809 27603 84.13
6 HGJ Status 72136 27278 37.81
7 Comissioning of Village 72136 34836 48.29
8 ROAD DISMENTLING/RESTORATION(KM) 173305 166625 96.15