Physical Progress Phase-2, 3 & 5 |
||||
---|---|---|---|---|
Sr.No. | Components | Taget | Achivement | % |
1 | 2 | 3 | 4 | 5 |
1 | Tubewell | 38355 | 37867 | 98.73 |
2 | Pump House | 38355 | 36516 | 95.21 |
3 | OHT | 36393 | 35686/11619 | 98.06 |
4 | Distribution (Line Laying in Km.) | 419563 | 419563 | 100.00 |
5 | Solar Plant | 32810 | 27848 | 84.88 |
6 | HGJ Status | 72134 | 28425 | 39.41 |
7 | Comissioning of Village | 72134 | 37018 | 51.32 |
8 | ROAD DISMENTLING/RESTORATION(KM) | 177431 | 173183 | 97.61 |