Citywise Discharge,STP Capacity and Gap Analysys

S.No. District City/Town River Present Population(in Lakhs) Population based sewage generation(MLD) Total Drains (Nos.) Discharge Through Drains (MLD) Discharge through sewer network (MLD) Total Discharge(MLD) No. of Existing STP capacity of Existing STP No. of STP Under Construction capacity of STP Under Construct ion (MLD) No. of STP Under Tenderi ng capacity of STP Under Tenderin g (MLD) Total Capacity (MLD) (9+11+13) Gap (MLD) (7-14) Capacity Proposed (MLD) Remark
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Total 399.68 4418.86 841 3954.45 1057.76 5012.21 134 4127.74 39 1141.8 13 490 5759.54 863.04 853.5 --
1 Agra Agra Yamuna 23.78 286.07 90 286.85 88 374.85 9 220.75 13 177.6 0 0 398.35 0.00 0 After construction of 13 Nos STPs of total capacity 177.60 MLD there will be no gap in Agra City
2 Aligarh Aligarh Aligarh Drain ( Irrigation ) 11.25 121.55 2 136.89 12.2 149.09 1 45 0 0 0 0 45.00 104.09 113 NMCG provided observations on DPR on 15.01.2024 and reply from CE Ganga sent to SMCG on 06.2.2024. SMCG asked for further clarifications on 04.04.2024. Clarification has been given on 07.06.2024
3 Ambedkar Nagar AKBARPUR Tamsa 1.45 15.70 6 19.41 0 19.41 0 0 0 0 0 0 0.00 19.41 0 N/A
Tanda Ghaghara 1.11 11.99 8 11.68 0 11.68 0 0 0 0 0 0 0.00 11.68 0 N/A
Ambedkar Nagar Total 2.56 27.69 14 31.09 0 31.09 0 0 0 0 0 0 0.00 31.09 0 --
4 Amethi Amethi Gomti 0 0 0 0.00 0 0 0 0 0 0 0.00 0.00 0 One diluted drain need not be tapped
5 Amroha Amroha Ganga 2.80 30.24 0 0 0 0.00 0 0 0 0 0 0 0.00 0.00 0 N/A
6 Auraiya Auraiya Yamuna 1.60 17.28 2 16.46 0 16.46 0 0 0 0 0 0 0.00 16.46 0 N/A
7 Ayodhya Ayodhya Saryu 3.40 36.72 21 30.87 12.5 43.37 2 18 1 33 0 0 51.00 0.00 0 N/A
8 Azamgarh Azamgarh Tamsa 1.45 15.75 22 22.46 0 22.46 0 0 1 8 0 0 8.00 14.46 0 N/A
9 Baghpat Baghpat Town Yamuna 0.94 10.00 4 8.6 0 8.60 1 14 0 0 0 0 14.00 0.00 0 N/A
10 Ballia Ballia Ganga 1.35 14.67 1 12.1 0 12.10 0 0 1 20 0 0 20.00 0.00 0 N/A
11 Banda Banda Ken 2.18 23.54 2 16.5 0 16.50 0 0 0 0 0 0 0.00 16.50 0 Bioremediation treatment is being done by Nagar palika ,Banda.
12 Barabanki Nawabganj Gomti 1.45 13.94 1 14 0 14.00 0 0 0 0 0 0 0.00 14.00 0 N/A
13 Bareilly Bareilly DEVRANIYA 11.36 122.66 1 0.87 25 25.87 1 35 1 1 0 0 36.00 0.00 0 N/A
NAKTIA RIVER 11 41.21 0 41.21 0 0 1 42 0 0 42.00 0.00 0 N/A
Ram ganga 1 18.82 0 18.82 0 0 1 20 0 0 20.00 0.00 0 25 mld stp with sewer network is proposed under Amrut.2
Bareilly Total 11.36 122.66 13 60.9 25 85.90 1 35 3 63 0 0 98.00 0.00 0 --
14 Bijnor Bijnor Ganga 1.35 24.00 2 11.05 0 11.05 1 24 0 0 0 0 24.00 0.00 0 N/A
15 Bulandshahr Anupshehar Ganga 0.37 2.56 2 2.56 2.5 5.06 4 5.06 0 0 0 0 5.06 0.00 0 N/A
Bulandshehar Kali 3.06 33.00 2 24 15 39.00 1 40 0 0 0 0 40.00 0.00 0 N/A
Gulaothi Kali 0.64 6.91 1 6.91 0 6.91 0 0 0 0 0 0 0.00 6.91 10 N/A
Narora Ganga 0.30 3.50 0 0 3.5 3.50 2 6.25 0 0 0 0 6.25 0.00 0 N/A
Bulandshahr Total 4.37 45.97 5 33.47 21 54.47 7 51.31 0 0 0 0 51.31 6.91 10 --
16 Chandauli Mugalsarai Ganga 1.67 18.13 2 29.33 0 29.33 0 0 0 0 0 0 0.00 29.33 37 DPR for 37MLD STP was sent to NMCG in 2021. TPA done in May-2023, NMCG has asked to revise the rates as per current SOR and finalize the land possession in May-2024. Fund to be allocated for purchase of land
17 Chitrakoot Chitrakoot Mandakini 16 0 0 0.00 1 3.42 0 0 0 0 3.42 0.00 0 N/A
Rajapur Yamuna 1 5 0 5.00 0 0 0 0 0 0 0.00 5.00 0 N/A
Chitrakoot Total 17 5 0 5.00 1 3.42 0 0 0 0 3.42 5.00 0 --
18 Deoria Gaura Barhaj Ghaghra 0.48 6.48 11 1.38 0 1.38 0 0 0 0 0 0 0.00 1.38 6 N/A
Lar Ghaghra 0.28 3.82 2 2.45 0 2.45 0 0 0 0 0 0 0.00 2.45 3 N/A
Deoria Total 0.76 10.30 13 3.83 0 3.83 0 0 0 0 0 0 0.00 3.83 9 --
19 Etah etah Ishan 15.05 16.00 1 4 12 16.00 1 24 0 0 0 0 24.00 0.00 0 There is no gap at present
20 Etawah Etawah Yamuna 3.04 32.92 2 30.99 0 30.99 3 44.95 0 0 0 0 44.95 0.00 0 There is no gap at present
Saifai Village Yamuna 0 0 1.4 1.40 1 1.6 0 0 0 0 1.60 0.00 0 There is no gap at present
Etawah Total 3.04 32.92 2 30.99 1.4 32.39 4 46.55 0 0 0 0 46.55 0.00 0 --
21 Farrukhabad Farrukhabad Ganga 2.90 31.32 5 29.5 0 29.50 0 0 1 30 0 0 30.00 0.00 0 Proposed to be tapped at 30 MLD STP at Farukhabad. Work in progress and Proposed to be completed by June, 2024.
Fatehgarh Ganga 1.45 15.66 3 15.07 0 15.07 1 2.7 1 17.7 0 0 20.40 0.00 0 Proposed to be tapped at 17.70 MLD STP at Fatehgarh. Work in progress and Proposed to be completed by June, 2024
Farrukhabad Total 4.35 46.98 8 44.57 0 44.57 1 2.7 2 47.7 0 0 50.40 0.00 0 --
22 Firozabad Firozabad Yamuna 8.61 93.00 2 54.26 5.5 59.76 2 70 0 0 0 0 70.00 0.00 0 There is no gap at present
23 Gautam Buddha Nagar Greater Noida Harnandi (Hindon) 9.15 98.00 0 0 0 0.00 4 174 0 0 0 0 174.00 0.00 0 N/A
Noida Yamuna 12.25 132.00 0 0 0 0.00 8 411 0 0 0 0 411.00 0.00 0 N/A
Gautam Buddha Nagar Total 21.40 230.00 0 0 0 0.00 12 585 0 0 0 0 585.00 0.00 0 --
24 Ghaziabad Ghaziabad Harnandi (Hindon) 32.60 352.00 8 306.49 0 306.49 11 535 0 0 0 0 535.00 0.00 0 N/A
Kali 0 0 0 0.00 1 3 0 0 0 0 3.00 0.00 0 N/A
Yamuna 2 52 0 52.00 0 0 0 0 0 0 0.00 52.00 0 N/A
Ghaziabad Total 32.60 352.00 10 358.49 0 358.49 12 538 0 0 0 0 538.00 52.00 0 --
25 Ghazipur Ghazipur Ganga 1.40 15.50 0 0 0 0.00 0 0 1 21 0 0 21.00 0.00 0 N/A
Saidpur Ganga 0.30 3.40 8 5.3 0 5.30 0 0 0 0 0 0 0.00 5.30 0 N/A
Zamania Ganga 0.44 5.05 3 4.41 0 4.41 0 0 0 0 0 0 0.00 4.41 0 N/A
Ghazipur Total 2.14 23.95 11 9.71 0 9.71 0 0 1 21 0 0 21.00 9.71 0 --
26 Gorakhpur Barhalganj Ghaghra 0.29 4.11 7 3.57 0 3.57 0 0 0 0 0 0 0.00 3.57 6 DPR for I&D work for 6 MLD STP in Barhalganj is submitted to NMCG by SMCG vide letter No- 170/702/SMCG-UP/02 Dated 26.02.2024.
Gorakhpur Ramgarhtal 8.02 124.38 24 47.82 0 47.82 3 50 0 0 0 0 50.00 0.00 0 N/A
Rapti 9 49.96 0 49.96 0 0 0 0 0 0 0.00 49.96 44 N/A
Rohini 6 27 0 27.00 0 0 2 40 0 0 40.00 0.00 0 N/A
Gorakhpur Total 8.31 128.49 46 128.35 0 128.35 3 50 2 40 0 0 90.00 53.53 50 --
27 Hamirpur Hamirpur Betwa 0.64 6.91 2 4.71 0 4.71 0 0 0 0 0 0 0.00 4.71 0 DPR for I&D work of this drain has been sent to SBM Nideshalay for approval by UPJN (U) in October,2023.
Yamuna 1 1.73 0 1.73 0 0 0 0 0 0 0.00 1.73 0 DPR for I&D work of this drain has been sent to SBM Nideshalay for approval by UPJN (U) in October,2023.
Hamirpur Total 0.64 6.91 3 6.44 0 6.44 0 0 0 0 0 0 0.00 6.44 0 --
28 Hapur Garmukteshwar Ganga 0.57 7.50 2 7.5 0 7.50 2 9 0 0 0 0 9.00 0.00 0 N/A
Hapur Kali 2.95 30.00 1 6 0 6.00 1 30 0 0 1 6 36.00 0.00 0 N/A
Hapur Total 3.52 37.50 3 13.5 0 13.50 3 39 0 0 1 6 45.00 0.00 0 --
29 Hardoi Hardoi Sai 2.70 29.16 0 0 0 0.00 0 0 0 0 0 0 0.00 0.00 0 Sample Was Taken At Confluence Point Of Chhuiya Drain At Sai River. DIscharge was found very less
30 Hathras Hathras Karvan 1.74 18.86 10 16.32 3.9 20.22 0 0 0 0 1 24 24.00 0.00 0 After construction of 1 No STP 24 MLD there will be no gap
31 Jalaun Kalpi Yamuna 1.15 12.42 1 11 0 11.00 0 0 0 0 0 0 0.00 11.00 0 DPR for I&D works has been sent to NMCG vide SMCG Letter no. 318/SMCG UP/376 dt. 30-03-2020. No communication received from NMCG.
32 Jaunpur Jaunpur Gomti 2.60 28.17 14 23.44 0 23.44 1 30 0 0 0 0 30.00 0.00 0 N/A
33 Jhansi Jhansi Pahunch 6.92 74.73 11 53 0 53.00 1 26 0 0 0 0 26.00 27.00 0 Tapped in Existing 26.00 MLD STP at Shivpuri Road maintained by Jhansi Nagar nigam. and 26 MLD STP Laxmital maintained by UPJN(U).
34 Kannauj Kannauj Ganga 1.33 14.36 3 14 0 14.00 1 13 0 0 0 0 13.00 1.00 0 Tapped in Existing 13.00 MLD STP maintained by UPJN (U)
35 Kanpur Dehat Kanpur Dehat Yamuna 1.89 20.41 1 4.61 0 4.61 0 0 0 0 0 0 0.00 4.61 0 DPR for I&D work of this drain has been sent to AMRUT Nideshalay for approval by UPJN (U) .
36 Kanpur Nagar Bithoor Ganga 0.15 1.70 7 1.3 0 1.30 0 0 0 0 0 0 0.00 1.30 0 Onsite Treatment at Bithoor.
Kanpur Nagar Ganga 35.50 426.00 17 187.12 66.75 253.87 3 188 0 0 0 0 188.00 65.87 0 Flow of drains go to 5/ 36/43/130 MLD STP/CETP, Jajmau and for 6 untapped drains DPR is pending for approval at NMCG from Nov, 2023.
Pandu 8 98.76 65.44 164.20 3 282 0 0 0 0 282.00 0.00 0 Flow of these drains go to 210 MLD STP Bingawan/42 MLD Sajari/30 MLD STP Panka and for 2 partially tapped drains DPR is pending for approval at NMCG from Nov, 2023.
Kanpur Nagar Total 35.65 427.70 32 287.18 132.19 419.37 6 470 0 0 0 0 470.00 67.17 0 --
37 Kasganj Kasganj kaali Nadi 1.12 12.17 2 12.76 0 12.76 1 15 0 0 0 0 15.00 0.00 0 There is no gap at present
38 Kaushambi Kaushambi Ganga 2 0.5 0 0.50 0 0 0 0 0 0 0.00 0.50 0 N/A
39 Lakhimpur Kheri Gola Gokaran Nath Sarayan 0.79 8.64 5 6.68 0 6.68 0 0 0 0 0 0 0.00 6.68 0 DPR has been prepared by U.P. Jal Nigam (Urban) in SBM 2.0 and submmited for approval.
ULL RIVER 3 8 0 8.00 0 0 0 0 0 0 0.00 8.00 0 Originating from Dist Lakhimpur & falls in Ghagra river.
Lakhimpur Kheri Total 0.79 8.64 8 14.68 0 14.68 0 0 0 0 0 0 0.00 14.68 0 --
40 Lalitpur Lalitpur Betwa 1.88 20.30 1 20 0 20.00 0 0 0 0 0 0 0.00 20.00 0 Bioremediation treatment is being done by Nagar palika , Lalitpur.
41 Lucknow Lucknow Gomti 38.10 457.20 32 550.98 173.55 724.53 7 465.5 3 209 0 0 674.50 50.03 198.5 Financial approval is pending from NMCG for 3.5 MLD STP since June-2023, DPR for 120MLD Vasantkunj submitted to NMCG on 16.01.2024 and DPR for 75MLD Bharwara has been submmited to NMCG for approval on dt. 27.09.2022. Request regarding approval of DPR dt. 03.06.2024 to Chief Engineer (Ganga) forwarding to NMCG.
Sai 1 54.78 0 54.78 0 0 0 0 1 100 100.00 0.00 0 Evaluation of Tender is in porgress
Lucknow Total 38.10 457.20 33 605.76 173.55 779.31 7 465.5 3 209 1 100 774.50 50.03 198.5 --
42 Mahoba Mahoba NA 1.32 14.25 7 10.7 0 10.70 0 0 0 0 0 0 0.00 10.70 0 Discharge of this drain is accumulates in Keerat Sagar, kalyan Sagar and Dariba pond.
43 Mainpuri mainpuri Ishan 0 0 13 13.00 1 23 0 0 0 0 23.00 0.00 0 There is no gap at present
44 Mathura Chhata Kosi Arterial Channel 0.36 3.94 14 2.63 0 2.63 0 0 0 0 1 6 6.00 0.00 0 After construction of 1 No STP 6 MLD there will be no gap
Govardhan Yamuna 0.22 2.43 2 1.54 2.3 3.84 1 2.76 0 0 0 0 2.76 1.08 4.5 4.50 MLD STP is proposed at goverdhan inder SBM 2.0 by UPJN(U),after which there shall be no gap.
Kosi Kalan Kosi Arterial Channel 0.81 8.82 1 5.64 0 5.64 0 0 0 0 1 12 12.00 0.00 0 After construction of 1 No STP 12 MLD there will be no gap
Mathura Yamuna 7.94 85.85 23 68.55 12 80.55 4 67.3 1 60 0 0 127.30 0.00 0 After construction of 1 No STP 60 MLD there will be no gap
Vrindavan Yamuna 1.51 17.00 13 11.49 0 11.49 2 12 1 13 0 0 25.00 0.00 0 After construction of 1 No STP 13 MLD there will be no gap
Mathura Total 10.84 118.04 53 89.85 14.3 104.15 7 82.06 2 73 2 18 173.06 1.08 4.5 --
45 Mau Dohrighat Ghaghara 0.15 1.69 5 2.21 0 2.21 0 0 0 0 0 0 0.00 2.21 0 DPR for 3.5MLD STP submitted to NMCG, on which NMCG suggested to go for FSTP. DPR for FSTP will be submitted upto 25.06.2024.
46 Meerut Kinauni Harnandi (Hindon) 0.06 0.67 0 0 0 0.00 0 0 0 0 0 0 0.00 0.00 0 N/A
Meerut Kali 18.52 222.24 3 307.22 26 333.22 14 179 1 220 0 0 399.00 0.00 60 Land acquisition is in process after which DPR will be prepared and submitted.
Sardhana Harnandi (Hindon) 0.81 8.75 0 0 0 0.00 0 0 0 0 0 0 0.00 0.00 0 N/A
Meerut Total 19.39 231.66 3 307.22 26 333.22 14 179 1 220 0 0 399.00 0.00 60 --
47 Mirzapur Chunar Ganga 0.40 4.41 0 0 0 0.00 0 0 0 0 0 0 0.00 0.00 0 N/A
Mirzapur Ganga 2.75 29.75 22 27.39 0 27.39 2 21 2 17 0 0 38.00 0.00 0 N/A
Mirzapur Total 3.15 34.16 22 27.39 0 27.39 2 21 2 17 0 0 38.00 0.00 0 --
48 Moradabad Moradabad Ram ganga 12.82 138.53 24 97.97 36 133.97 2 78 1 25 0 0 103.00 30.97 80 DPR amounting capex cost Rs. 212.96 cr. and opex cost Rs. 323.29 cr. Total cost Rs. 536.25 cr. has been sent to NMCG for approval 35 MLD STP for zone-3 and 45 MLD STP for zone-4 hav been proposed
49 Muzaffarnagar Budhana Harnandi (Hindon) 0.75 8.10 3 7.4 0 7.40 1 10 0 0 0 0 10.00 0.00 0 N/A
Muzaffarnagar Kali West 5.56 60.05 7 51.09 7.44 58.53 1 32.5 1 54.5 0 0 87.00 0.00 0 N/A
Muzaffarnagar Total 6.31 68.15 10 58.49 7.44 65.93 2 42.5 1 54.5 0 0 97.00 0.00 0 --
50 Pilibhit Pilibhit Ganga 1.68 13.36 3 90 0 90.00 0 0 0 0 0 0 0.00 90.00 0 N/A
51 Pratapgarh Manikpur Ganga 0.20 2.12 5 1.59 0 1.59 0 0 0 0 0 0 0.00 1.59 0 N/A
Pratapgarh Sai 4 7.1 0 7.10 1 8.95 0 0 0 0 8.95 0.00 0 N/A
Pratapgarh Total 0.20 2.12 9 8.69 0 8.69 1 8.95 0 0 0 0 8.95 1.59 0 --
52 PrayagRaj Prayagraj Ganga 20.63 247.56 46 166.48 92.09 258.57 7 168 1 43 1 90 301.00 0.00 28 DPR submitted for 28 MLD on16.10.2023 to meet the gap of year 2037
Yamuna 30 122.11 86.22 208.33 4 172 0 0 1 50 222.00 0.00 25 DPR for 25 MLD is under preparation and will be submitted by 15.07.2024
PrayagRaj Total 20.63 247.56 76 288.59 178.31 466.90 11 340 1 43 2 140 523.00 0.00 53 --
53 Rae Bareli Dalmau Ganga 0.11 1.25 9 2.12 0 2.12 0 0 0 0 0 0 0.00 2.12 0 DPR OF 06 KLD FSTP HAS BEEN SUBMITTED TO NMCG ON DATE 27.09.2022. TPA IS COMPLETED,
Sai 7 32.8 0 32.80 1 18 0 0 0 0 18.00 14.80 0 DPR will be prepared after acquisition of Land for I&D of 02 drains which is to be provided by NPP
Rae Bareli Total 0.11 1.25 16 34.92 0 34.92 1 18 0 0 0 0 18.00 16.92 0 --
54 Rampur Rampur Ram ganga 3.77 44.47 3 33.39 0 33.39 3 34 0 0 0 0 34.00 0.00 0 N/A
55 Saharanpur Deoband Kali West 1.35 14.58 4 15.65 0 15.65 0 0 0 0 0 0 0.00 15.65 20 DPR for 20MLD STP is submitted to NMCG on 05.06.2023. TPA done on 09.03.2024. Approval is pending From NMCG.
Saharanpur Harnandi (Hindon) 10.01 120.12 99 97.64 24 121.64 1 38 0 0 1 135 173.00 0.00 0 N/A
Saharanpur Total 11.36 134.70 103 113.29 24 137.29 1 38 0 0 1 135 173.00 15.65 20 --
56 Sambhal Sambhal Ganga 3.12 33.69 0 0 0 0.00 0 0 0 0 0 0 0.00 0.00 0 N/A
57 Sant Ravidas Nagar Bhadohi Morwa 1.18 12.77 1 3.4 0 3.40 0 0 0 0 0 0 0.00 3.40 5.5 N/A
Varuna 2 11.5 0 11.50 0 0 0 0 0 0 0.00 11.50 18 DPR sent to NMCG by SMCG on 18.09.2023. Observations are received in March 2024 to which compliance shall be sent by 30.06.2024
Sant Ravidas Nagar Total 1.18 12.77 3 14.9 0 14.90 0 0 0 0 0 0 0.00 14.90 23.5 --
58 Shahjahanpur Shahjahanpur Khannaut 4.66 50.32 0 0 0 0.00 1 40 0 0 0 0 40.00 0.00 0 N/A
59 Shamli Banat Krishni 0.29 3.16 3 3.07 0 3.07 0 0 0 0 1 5 5.00 0.00 0 N/A
Bantikhera & Babri Krishni 0.27 3.03 1 3 0 3.00 0 0 0 0 1 5 5.00 0.00 0 N/A
Kairana Yamuna 1.24 13.39 1 10.5 0 10.50 0 0 1 15 0 0 15.00 0.00 0 N/A
Shamli Krishni 1.51 16.31 1 20.1 0 20.10 0 0 0 0 1 40 40.00 0.00 0 N/A
Thanabhawan Krishni 0.50 5.40 5 6.7 0 6.70 0 0 0 0 1 10 10.00 0.00 0 N/A
Shamli Total 3.81 41.29 11 43.37 0 43.37 0 0 1 15 4 60 75.00 0.00 0 --
60 Sitapur Sitapur Sarayan 2.07 22.35 21 12.72 0 12.72 0 0 0 0 0 0 0.00 12.72 0 PFR for I&D of drains amount Rs. 306.81 Cr. has been send to NMCG for approval on dt. 07.04.2021. Observations raised by NMCG on dt. 12.06.2024
61 Sultanpur Sultanpur Gomti 1.33 14.36 5 13.94 0 13.94 3 17 0 0 0 0 17.00 0.00 0 Extra Work of Boundarywall, Fixing of Handrailing at 10 MLD STP, Drain Lining of Karundiya Drain and Installation of SCADA etc is still pending.
62 Unnao Shuklaganj Ganga 1.13 12.24 7 11.96 0 11.96 0 0 1 5 0 0 5.00 6.96 0 Total 7 drains are discharging into River Ganga in NPP Shuklaganj out of which 5 drains of discharge 4.66 MLD has to be Intercepted & Diverted to under Construction 5 MLD STP Shuklaganj and rest of the 02 drains of discharge 7.3 MLD has to be tapped & treated by U.P. J.N. (Urban) under SBM 2 programme.
Unnao Ganga 2.22 24.02 1 11.36 0 11.36 0 0 1 15 0 0 15.00 0.00 0 STP 4-6 Hrs operating daily receiving average discharge 4MLD from 07.11.2023 through temporary line. Gravity main sewer line de-silting work till date 2.885 km. sewer line has been cleaned out of total 3.2 km. Cleaning of 0.315 km sewer line is balance till date. From last own week KRMPL not deployed manpower at site for cleaning of Sewer line.
Unnao Total 3.35 36.26 8 23.32 0 23.32 0 0 2 20 0 0 20.00 6.96 0 --
63 Varanasi Varanasi Assi 20.63 247.50 1 78 0 78.00 1 50 1 55 0 0 105.00 0.00 0 N/A
Ganga 28 75.73 141.27 217.00 4 110 0 0 1 7 117.00 100.00 140 There are 02 partially tapped drains for which construction of 55 MLD STP is in progress under Namami Gange. For 01 untapped drains, 07 MLD STP is sanctioned under AMRUT 2.0 which is under tendering.
Varuna 15 96.8 130.2 227.00 2 260 0 0 0 0 260.00 0.00 55 For 01 untapped Durga drain, DPR is sent to NMCG in April 2022 for approval. 01 partially tapped drain is to be taken up by UPJN(Urban).
Varanasi Total 20.63 247.50 44 250.53 271.47 522.00 7 420 1 55 1 7 482.00 100.00 195 --