Status of CETP in Uttar Pradesh Under Namami Gange Programme

S No Project Name Nodal Agency Executive Agency  Contractor / Firm Name Date of Sanction Date of start Date of Completion Sanction cost(Cr) Agreement Cost(Cr) Financial Progress(Cr) Physical Progress(%) Remarks
1 2 3 4 5 6 7 8 9 10 11 12 13
1 Construction of 20 MLD CETP at Jajmau Kanpur NMCG Jajamau Tanners and effluent treatment Va Tech Wabag 11-Feb-2019 11-Apr-2019 01-Apr-2024 617.00 520.14 +0 353.00 +0 92.00 Under Commisioning.
2 Upgradation of 2.15 MLD CETP to 2.15 MLD CETP at Unnnao NMCG Unnao Tanners and pollution control company M/s JV UTIPL-Oasis-SIMA 26-Jun-2022 127.00 172.00 +0 0.00 +0 0.00 LOA issued to L1 Bidder dated 7 th September 2023. Agreement signing Pending at the level of SPV.
3 Upgrdation of 4.5 MLD CETP at Banther , Unnao NMCG Banther Industrial Pollution Control company M/S EMS infracon 21-Feb-2020 07-Feb-2022 01-Sep-2024 108.96 111.96 +0 22.00 +0 46.00 Work Under Progress
4 Construction of 7.5 MLD CETP at GIDA, Gorakhpur NMCG M/S GIDA CETP Foundation -- 11-Jan-2022 93.52 0.00 +0 0.00 +0 0.00 Capacity of Plant has been reevaluated to 4 MLD as effluent water of IGL(Distillery unit) and electroplating industry cannot be treated at CETP. Instructions for preparation of revised DPR issued vide NMCG letter dated 18.04.2024 to GIDA & UPJN(U).UPJN(U) has refused to prepare the DPR Citing lack of technical expertise.