1 |
Gorakhpur |
|
I & D and Treatment for Barhalganj 7 Drains Falling in Ghaghra River. |
Kango Ghat Nala - 1 |
Untapped Drains |
Observation by NMCG dated 26/06/2024 was received regarding high COD/BOD. Regarding which COD/BOD test of 7drains is being done again, whose report will be submitted before 31/08/2024 |
28-Aug-2024 03:31 PM |
2 |
Gorakhpur |
|
I & D and Treatment for Barhalganj 7 Drains Falling in Ghaghra River. |
Kango Ghat Nala - 2 |
Untapped Drains |
Observation by NMCG dated 26/06/2024 was received regarding high COD/BOD. Regarding which COD/BOD test of 7drains is being done again, whose report will be submitted before 31/08/2024 |
28-Aug-2024 03:32 PM |
3 |
Gorakhpur |
|
I & D and Treatment for Barhalganj 7 Drains Falling in Ghaghra River. |
Tarkulahi Nala |
Untapped Drains |
Observation by NMCG dated 26/06/2024 was received regarding high COD/BOD. Regarding which COD/BOD test of 7drains is being done again, whose report will be submitted before 31/08/2024 |
28-Aug-2024 03:32 PM |
4 |
Gorakhpur |
|
I & D and Treatment for Barhalganj 7 Drains Falling in Ghaghra River. |
Kutiya Mohalla Nala |
Untapped Drains |
Observation by NMCG dated 26/06/2024 was received regarding high COD/BOD. Regarding which COD/BOD test of 7drains is being done again, whose report will be submitted before 31/08/2024 |
28-Aug-2024 03:33 PM |
5 |
Gorakhpur |
|
I & D and Treatment for Barhalganj 7 Drains Falling in Ghaghra River. |
Hanuman Garhi Nala |
Untapped Drains |
Observation by NMCG dated 26/06/2024 was received regarding high COD/BOD. Regarding which COD/BOD test of 7drains is being done again, whose report will be submitted before 31/08/2024 |
28-Aug-2024 03:33 PM |
6 |
Gorakhpur |
|
I & D and Treatment for Barhalganj 7 Drains Falling in Ghaghra River. |
Muktipath Near Bridge Nala |
Untapped Drains |
Observation by NMCG dated 26/06/2024 was received regarding high COD/BOD. Regarding which COD/BOD test of 7drains is being done again, whose report will be submitted before 31/08/2024 |
28-Aug-2024 03:33 PM |
7 |
Gorakhpur |
|
I & D and Treatment for Barhalganj 7 Drains Falling in Ghaghra River. |
Muktipath Nala |
Untapped Drains |
Observation by NMCG dated 26/06/2024 was received regarding high COD/BOD. Regarding which COD/BOD test of 7drains is being done again, whose report will be submitted before 31/08/2024 |
28-Aug-2024 03:34 PM |