1 |
Lucknow |
Lucknow |
Pollution Abatement Of Gomti River (Phase 1 Part 1) Lucknow |
Pata Nala |
Tapped Drains |
Tapped to 39 MLD STP at Daulatganj. 39 MLD STP construction work completed and Trial & Run is in progress. |
30-Oct-2024 03:02 PM |
2 |
Lucknow |
Lucknow |
Pollution Abatement Of Gomti River (Phase 1 Part 1) Lucknow |
Barikala Drain |
Untapped Drains |
Date of start of 3.5 MLD Barikala STP is given on dt. 07.09.2024 to M/s R.K. Engineers Sales Ltd. - Khilari Infrastructures (JV). Presently STP site is submerged due to rain water. Presently Dewatering work is in progress. |
14-Nov-2024 11:45 AM |