Jal Jeevan Mission-District Dashboard

Heirarchy Details
Total Bolock :
Total Panchayat :
Total Villages :
Scheme/Agency Details
No Of Agency :
SLSSC Scheme :
Jal Nigam Scheme :
District Progress
Total Villages :
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Cirtified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Village Status
Jal Nigam Villages :
Urbanized Villages :
Un Inhabitant :
less than 100 Population :
Yet to be alloted :
NGO :
NTD :
SLSSC Data Required :
Alloted to agency but SLSSC Not Done :
Agency Progress Details
Sr.No. Agency No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 JMC - Lakshmi (JV) 302 396 152147 93.93% 161982 90 32
2 Rithwik-Koya (JV) 378 642 141507 77.99% 181440 60 4
3 T.B.D. Descope Villages 37 48 16293 85.12% 19141 4 1
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 735 728 99.05
2 Pump House 735 693 94.29
3 Chlorination system 108 66 61.11
4 OHT 719 683/54 94.99
5 Distribution (Line Laying in Km.) 7283 6668 91.56
6 Solar Plant 569 548 96.31
7 F.H.T.C. 26610919 22756461 85.52
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 2808 2621 93.34
10 Villages where 100 % road restoration completed 96810 51349 53.04
;