Jal Jeevan Mission-District Dashboard

Heirarchy Details
Total Bolock :
Total Panchayat :
Total Villages :
Scheme/Agency Details
No Of Agency :
SLSSC Scheme :
Jal Nigam Scheme :
District Progress
Total Villages :
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Cirtified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Village Status
Jal Nigam Villages :
Urbanized Villages :
Un Inhabitant :
less than 100 Population :
Yet to be alloted :
NGO :
NTD :
SLSSC Data Required :
Alloted to agency but SLSSC Not Done :
Agency Progress Details
Sr.No. Agency No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 ION EXCHANGE 155 206 62222 81.08% 76744 52 4
2 JMC - Lakshmi (JV) 151 207 49045 77.06% 63644 48 15
3 PNC-SPML-JV 418 654 221725 87.31% 253962 172 40
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 730 727 99.59
2 Pump House 730 708 96.99
3 Chlorination system 331 276 83.38
4 OHT 728 723/95 99.31
5 Distribution (Line Laying in Km.) 7172 6871 95.80
6 Solar Plant 617 443 71.80
7 F.H.T.C. 26610919 22756461 85.52
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 2022 1932 95.55
10 Villages where 100 % road restoration completed 96810 51349 53.04
;