Jal Jeevan Mission-Agency Dashboard

Heirarchy Details
Assign District:
Assign Scheme :
Assign Villages :
Physical Progress
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Cirtified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Agency Progress Details
Sr.No. District No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Shamli 169 221 85590 92.39% 92644 175 8
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 172 171 99.42
2 Pump House 172 169 98.26
3 Chlorination system 26 18 69.23
4 OHT 172 167/21 97.09
5 Distribution (Line Laying in Km.) 1286 1150 89.42
6 Solar Plant 153 117 76.47
7 F.H.T.C. 26610919 22756461 85.52
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 712 630 88.48
10 Villages where 100 % road restoration completed 96810 51349 53.04