Jal Jeevan Mission-Agency Dashboard

Heirarchy Details
Assign District:
Assign Scheme :
Assign Villages :
Physical Progress
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Cirtified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Agency Progress Details
Sr.No. District No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Kushi Nagar 454 910 297380 88.29% 336835 512 232
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 454 454 100.00
2 Pump House 454 448 98.68
3 Chlorination system 389 217 55.78
4 OHT 454 451/161 99.34
5 Distribution (Line Laying in Km.) 6447 5847 90.69
6 Solar Plant 360 304 84.44
7 F.H.T.C. 26610919 22756461 85.52
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 1816 1786 98.35
10 Villages where 100 % road restoration completed 96810 51349 53.04