Jal Jeevan Mission-Agency Dashboard

Heirarchy Details
Assign District:
Assign Scheme :
Assign Villages :
Physical Progress
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Cirtified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Agency Progress Details
Sr.No. District No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Gorakhpur 627 1533 236430 91.96% 257110 1035 445
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 636 637 100.00
2 Pump House 636 636 100.00
3 Chlorination system 534 388 72.66
4 OHT 629 629/393 100.00
5 Distribution (Line Laying in Km.) 7008 6835 97.53
6 Solar Plant 623 579 92.94
7 F.H.T.C. 26610919 22756461 85.52
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 2605 2527 97.01
10 Villages where 100 % road restoration completed 96810 51349 53.04