Physical Progress
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Cirtified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Agency Progress Details
Sr.No. District No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Maharajganj 37 48 16293 85.12% 19141 4 1
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 39 38 97.44
2 Pump House 39 37 94.87
3 Chlorination system 0 0 0.00
4 OHT 37 37/0 100.00
5 Distribution (Line Laying in Km.) 342 278 81.29
6 Solar Plant 25 23 92.00
7 F.H.T.C. 26610919 22756461 85.52
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 74 66 89.19
10 Villages where 100 % road restoration completed 96810 51349 53.04