Jal Jeevan Mission-Agency Dashboard

Heirarchy Details
Assign District:
Assign Scheme :
Assign Villages :
Physical Progress
Households :
FHTC :
FHTC(%) :
Total HGJ :
Total Cirtified :
HO Villages :
Incoming Complaints Received
All Complaints :
Close Complaints :
Pending Complaints :
Feedback from Gram Pradhan On Call
All Complaints :
Close Complaints :
Pending Complaints :
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
Expenditure :
Expenditure(%) :
Agency Progress Details
Sr.No. District No Of Scheme No Of Village households FHTC FHTC % Har Gar Gal Certified
1 2 3 4 5 6 7 8 9
1 Ambedkar Nagar 62 238 36387 96.11% 37858 131 43
Components Wise Physical Progress
Sr.No. Components Taget Achivement %
1 2 3 4 5
1 Tubewell 62 62 100.00
2 Pump House 62 61 98.39
3 Chlorination system 29 19 65.52
4 OHT 62 62/29 100.00
5 Distribution (Line Laying in Km.) 1152 1150 99.83
6 Solar Plant 62 62 100.00
7 F.H.T.C. 26646826 22934730 86.07
8 W.T.P.
9 ROAD DISMENTLING/RESTORATION(KM) 261 252 96.55
10 Villages where 100 % road restoration completed 96810 54429 56.22
11 Comissioning of Village 238 155 65.13
12 Regular water supply 238 170 71.43