I&D of Drains and STP works in Unnao (15MLD) |
City Jail Drain (Dakari drain) |
Tapped Drains |
The overall progress of the project is 99.00%. All works (Civil/Electrical & Mechanical) of the STP has been completed. Desilting & Relaying gravity line is unfeasible (soil liquefaction). Alternative pumping IPS with 2.30KM Rising main 450 DI K-9 pipe arrangement proposed (Technical Solution). Consequently, labor requirements and final project completion date remain unfinalized due to Alternative technical proposal is yet to be decided by NMCG. In this regard, the executing agency submitted a proposal vide Letter No. UPJN/KRMPL/Kanpur/2025-26/4567 dated 31-08-2026 |