1 |
Mathura |
Mathura |
Rehabilation / Upgradation of Mathura Sewerage Scheme |
Akhkunda Ghat |
Tapped Drains |
Tapped to 14.5 MLD STP at Trans Yamuna |
01-Jul-2024 12:00 AM |
2 |
Mathura |
Mathura |
Rehabilation / Upgradation of Mathura Sewerage Scheme |
Bengali Ghat (Outfall) |
Tapped Drains |
Tapped to 14.5 MLD STP at Trans Yamuna |
01-Jul-2024 12:00 AM |
3 |
Mathura |
Mathura |
Rehabilation / Upgradation of Mathura Sewerage Scheme |
Chintaharan Nala |
Tapped Drains |
Tapped to 14.5 MLD STP at Trans Yamuna |
01-Jul-2024 12:00 AM |
4 |
Mathura |
Mathura |
Rehabilation / Upgradation of Mathura Sewerage Scheme |
Daula Maula Nala |
Tapped Drains |
Tapped to 14.5 MLD STP at Trans Yamuna |
01-Jul-2024 12:00 AM |
5 |
Mathura |
Mathura |
Rehabilation / Upgradation of Mathura Sewerage Scheme |
Gaughat Nala |
Tapped Drains |
Tapped to 14.5 MLD STP at Trans Yamuna |
01-Jul-2024 12:00 AM |
6 |
Mathura |
Mathura |
Rehabilation / Upgradation of Mathura Sewerage Scheme |
Rani Ghat Nala |
Tapped Drains |
Tapped to 14.5 MLD STP at Trans Yamuna |
01-Jul-2024 12:00 AM |
7 |
Mathura |
Mathura |
Rehabilation / Upgradation of Mathura Sewerage Scheme |
Swami Ghat Nala |
Tapped Drains |
Tapped to 14.5 MLD STP at Trans Yamuna |
01-Jul-2024 12:00 AM |
8 |
Mathura |
Mathura |
Rehabilation / Upgradation of Mathura Sewerage Scheme |
Vishram Ghat |
Tapped Drains |
Tapped to 14.5 MLD STP at Trans Yamuna |
01-Jul-2024 12:00 AM |
9 |
Mathura |
Mathura |
Rehabilation / Upgradation of Mathura Sewerage Scheme |
Dhruv Ghat Nala |
Tapped Drains |
Tapped to 16.0 MLD, Laxmi Nagar, Trans Yamuna |
01-Jul-2024 12:00 AM |
10 |
Mathura |
Mathura |
Rehabilation / Upgradation of Mathura Sewerage Scheme |
Cant Nala |
Tapped Drains |
Tapped to 16.0 MLD, Laxmi Nagar, Trans Yamuna |
01-Jul-2024 12:00 AM |
11 |
Mathura |
Mathura |
Rehabilation / Upgradation of Mathura Sewerage Scheme |
Satrangi Nala |
Tapped Drains |
Tapped to 16.0 MLD, Laxmi Nagar, Trans Yamuna |
01-Jul-2024 12:00 AM |
12 |
Mathura |
Mathura |
Rehabilation / Upgradation of Mathura Sewerage Scheme |
Mahadev Ghat(Sadar Bazar Nala) |
Tapped Drains |
Tapped to 16.0 MLD, Laxmi Nagar, Trans Yamuna |
01-Jul-2024 12:00 AM |
13 |
Mathura |
Mathura |
Rehabilation / Upgradation of Mathura Sewerage Scheme |
Dairy Farm Nala |
Tapped Drains |
Tapped to 16.0 MLD, Laxmi Nagar, Trans Yamuna |
01-Jul-2024 12:00 AM |
14 |
Mathura |
Mathura |
Rehabilation / Upgradation of Mathura Sewerage Scheme |
Chakratirath Nala |
Tapped Drains |
Tapped to 6.8 MLD and 30 MLD STP at Masani. |
01-Jul-2024 12:00 AM |
15 |
Mathura |
Mathura |
Rehabilation / Upgradation of Mathura Sewerage Scheme |
Krishan Ganga Nala |
Tapped Drains |
Tapped to 6.8 MLD and 30 MLD STP at Masani. |
01-Jul-2024 12:00 AM |
16 |
Mathura |
Mathura |
Rehabilation / Upgradation of Mathura Sewerage Scheme |
Octroi Post Nala |
Tapped Drains |
Tapped to 6.8 MLD and 30 MLD STP at Masani. |
01-Jul-2024 12:00 AM |
17 |
Mathura |
Mathura |
Rehabilation / Upgradation of Mathura Sewerage Scheme |
Jaisinghpura Nala |
Tapped Drains |
Tapped to 6.8 MLD and 30 MLD STP at Masani. |
01-Jul-2024 12:00 AM |
18 |
Mathura |
Mathura |
Rehabilation / Upgradation of Mathura Sewerage Scheme |
Shahaganj Nala |
Tapped Drains |
Tapped to 6.8 MLD and 30 MLD STP at Masani. |
01-Jul-2024 12:00 AM |
19 |
Mathura |
Mathura |
Rehabilation / Upgradation of Mathura Sewerage Scheme |
Masani Nala |
Tapped Drains |
Tapped to 30 MLD STP at Mathura. |
01-Jul-2024 12:00 AM |