U.P. Pollution Control Board
STP - Under Tendering July -23
S.No Name of District/town No of STP(s) Capacity (MLD) Expected date of Commissioning Status of Project
 (at DPR Stage/ Under Tendering/Work to be Awarded)
1 Meerut 1 220 Jun, 2025 LOA has been issued to the firm on 27.05.2023.
2 Saharanpur 1 135 Jun, 2025 Technical bids were opened on 23.03.2023. 6 bids were received which have been evaluated. Evaluation report has been submitted to NMCG on 24.05.2023. After the approval from NMCG, financial bids will be opened.
3 Varanasi 1 55 Jun, 2025 Technical bids were opened on 06.03.2023. 9 bids were received which have been evaluated. Evaluation report has been submitted to NMCG on 24.05.2023. Observations were received from NMCG over the TBR , reply to NMCG has been sent on date 03.07.2023. After approval from NMCG , financial bids will be opened.
4 Varanasi (Durga Drain) 1 55 24 months after issuance of effective date of start DPR is under TPA
5 Mathura 1 60 Jun, 2025 Technical bids were opened on 03.04.2023. 4 bids were received which have been evaluated. Financial bids were opened on 30.05.2023 and financial bid evaluation report sent to NMCG on 14.07.2023.
6 Loniyapurva,
Lucknow
1 50 Jun, 2025 Last date for submission of bids is 22.06.2023 and 8 bids have been received which are under evaluation.
7 Hathras 1 24 Jun, 2025 Technical bid were opened on 26.06.2023. 7 bids were received which are under evaluation.
8 Prayagraj
(Distt. C)
1 43 Jun, 2025 Project has been sanctioned vide NMCG letter dated 14.03.2023. Bid documents were submitted to NMCG on 01.04.2023. Observations on bid documents have been intimated by NMCG on 03.05.2023. Technical bids were opened on 17.07.2023. 10 bids have been received which are under evaluation.
9 Prayagraj 2 55.4 Dec, 2025 1 DPR is under review in NMCG since May, 22 and 1 DPR is to be included as variation in ongoing NMCG project at Prayagraj.
10 Prayagraj
(Distt. D)
1 90 Jun, 2025 Technical bids were opened on 08.06.2023. 8 bids have been received which are under evaluation.
11 Shamli Town 1 40 Jun, 2025 Bid documents has been prepared and submitted to NMCG for evaluation. After approval of bid document NIT will be issued.
12 Banat Town, distt.
Shamli
1 5
13 Thanabhawan town,
distt. Shamli
1 10
14 Babri-Bantikhera,
distt Shamli
1 5
15 Bijnaur, Lucknow
Phase II, Part - 2
1 100 24 months after issuance of effective date of start DPR is under TPA
16 Bharwara, Lucknow
Phase -III
1 75 24 months after issuance of effective date of start DPR is under TPA
17 Manikpur 1 2.4 24 months after issuance of effective date of start Revised DPR was submitted to NMCG on 18.08.2022.
18 Mau 1 3.5 24 months after issuance of effective date of start Revised DPR was submitted to NMCG on 04.12.2022.Observation on DPR received on 11.07.2023.
19 Dalmau, RaeBareli 1 0.006 24 months after issuance of effective date of start DPR is under TPA
20 Tanda, Ambedkar Nagar 1 15 24 months after issuance of effective date of start Revised DPR was submitted to SMCG on 24.05.2023. Observations have been intimated by SMCG vide letter dated 07.06.2023.
21 Hapur  1 6 24 months after issuance of effective date of start Revised DPR was submitted to NMCG on 24.01.2023.
22 Gulaothi, Bulandshahr 1 10 24 months after issuance of effective date of start DPR is under TPA
23 Deoband 1 20 24 months after issuance of effective date of start DPR was submitted to NMCG on 05.06.2023.
24 Moradabad (Zone III) 1 43 24 months after issuance of effective date of start Revised DPR was submitted to NMCG on 02.06.2023 .
25 Aligarh 2 113 24 months after issuance of effective date of start DPR is under TPA
26 Kosi 1 12 Jun, 2025 Technical bid were opened on 26.06.2023. 9 bids were received which are under evaluation.
27 Chhata 1 6 Jun, 2025 Technical bid were opened on 26.06.2023. 2 bids were received which are under evaluation.
28 Vrindavan 1 13 Jun, 2025 Technical bid were opened on 26.06.2023. 6 bids were received which are under evaluation.
29 Gorakhpur 1 44 24 months after issuance of effective date of start Revised DPR was submitted to NMCG on 04.11.2022.Observations have been intimated by NMCG vide letter dated 09.06.2023.
30 Chandauli 1 37 24 months after issuance of effective date of start DPR is under TPA
31 Barhalganj, Gorakhpur 1 6 24 months after issuance of effective date of start Revised DPR was submitted to NMCG on 16.01.2023. Observations have been intimated by NMCG vide letter dated 09.06.2023.
32 Kanpur 1 - 24 months after issuance of effective date of start DPR was submitted to NMCG on 08.03.2023.
Total 34 1353.306    
   Source : MPR provided by UP Jal Nigam.