| 1 |
Pratapgarh |
6823817 |
Jariyari PWS |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
102.49 |
91.84 |
0.00 |
0.00 |
10.65 |
102.49 |
Under Construction |
0.00 |
1. Due to fund Diversion Progress of work is interrupted for about 10 years.
2. Inquiry against Concerning employees (For Fund Diversion) is under Process at HQ Level. 3. Presently For completing the scheme as per JJM Norms Work is under Sanction at Sashan Level. |
| 2 |
Pratapgarh |
6824799 |
Madaipur pws |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
130.28 |
116.55 |
78.39 |
0.00 |
13.73 |
130.28 |
Under Construction |
68.00 |
1. Due to fund Diversion Progress of work is interrupted for about 10 years.
2. Inquiry against Concerning employees (For Fund Diversion) is under Process at HQ Level. 3. Presently For completing the scheme as per JJM Norms Work is under Sanction at Sashan Level. |
| 3 |
Pratapgarh |
6824800 |
Majhgawan pws |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
93.46 |
83.64 |
20.00 |
0.00 |
9.82 |
93.46 |
Under Construction |
26.00 |
1. Due to fund Diversion Progress of work is interrupted for about 10 years.
2. Inquiry against Concerning employees (For Fund Diversion) is under Process at HQ Level. 3. Presently For completing the scheme as per JJM Norms Work is under Sanction at Sashan Level. |
| 4 |
Pratapgarh |
6824811 |
Puremadho Singh pws |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
73.00 |
65.57 |
25.00 |
0.00 |
7.43 |
73.00 |
Under Construction |
22.00 |
1. Due to fund Diversion Progress of work is interrupted for about 10 years.
2. Inquiry against Concerning employees (For Fund Diversion) is under Process at HQ Level. 3. Presently For completing the scheme as per JJM Norms Work is under Sanction at Sashan Level. |
| 5 |
Pratapgarh |
6824815 |
Sadaha pws |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
150.45 |
134.51 |
61.90 |
0.00 |
15.94 |
150.45 |
Under Construction |
46.00 |
1. Due to fund Diversion Progress of work is interrupted for about 10 years.
2. Inquiry against Concerning employees (For Fund Diversion) is under Process at HQ Level. 3. Presently For completing the scheme as per JJM Norms Work is under Sanction at Sashan Level. |
| 6 |
Pratapgarh |
6824820 |
Setapur pws |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
122.67 |
108.82 |
20.04 |
0.00 |
13.85 |
122.67 |
Under Construction |
16.00 |
1. Due to fund Diversion Progress of work is interrupted for about 10 years.
2. Inquiry against Concerning employees (For Fund Diversion) is under Process at HQ Level. 3. Presently For completing the scheme as per JJM Norms Work is under Sanction at Sashan Level. |
| 7 |
Pratapgarh |
6824823 |
Vikrampur pws |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
175.42 |
156.57 |
0.00 |
0.00 |
18.85 |
175.42 |
Under Construction |
0.00 |
1. Due to fund Diversion Progress of work is interrupted for about 10 years.
2. Inquiry against Concerning employees (For Fund Diversion) is under Process at HQ Level. 3. Presently For completing the scheme as per JJM Norms Work is under Sanction at Sashan Level. |
| 8 |
Pratapgarh |
7386081 |
Pure Rajju QPV Scheme 2015 16 |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
117.15 |
104.72 |
73.76 |
0.00 |
12.43 |
117.15 |
Under Construction |
60.00 |
1. Due to fund Diversion Progress of work is interrupted for about 10 years.
2. Inquiry against Concerning employees (For Fund Diversion) is under Process at HQ Level. 3. Presently For completing the scheme as per JJM Norms Work is under Sanction at Sashan Level. |
| 9 |
Pratapgarh |
7617897 |
Dherahna QPV Scheme 2016 17 |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
113.41 |
101.39 |
0.00 |
0.00 |
12.02 |
113.41 |
Under Construction |
0.00 |
1. Due to fund Diversion Progress of work is interrupted for about 10 years.
2. Inquiry against Concerning employees (For Fund Diversion) is under Process at HQ Level. 3. Presently For completing the scheme as per JJM Norms Work is under Sanction at Sashan Level. |
| 10 |
Pratapgarh |
7889551 |
Bibiya Karanpur PWS Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
212.74 |
1.76 |
1.76 |
0.00 |
210.98 |
212.74 |
Under Construction |
0.00 |
1.Due to Saline water Progress of work could not be continued. 2. DPR is being revised by identifying new land at nearby village for Tube Well with required Rising Main. 3.Revised DPR/Proposal shall be submitted by 30.11.2026. |
| 11 |
Pratapgarh |
8130426 |
Manaitapur Gram Panchayat Water Supply Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
139.37 |
0.26 |
0.26 |
0.00 |
139.11 |
139.37 |
Under Construction |
50.00 |
Work in Progress (T.well- 100%, Pipe Line- 75%, OHT-5%,FHTC-0/258) |
| 12 |
Pratapgarh |
8130432 |
Dulhipur Gram Panchayat Water Supply Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
154.77 |
56.08 |
56.08 |
0.00 |
98.69 |
154.77 |
Under Construction |
83.00 |
Work in Progress (T.well- 100%, Pump House-70%,Pipe Line- 90%, OHT-60%,FHTC-190/474) |
| 13 |
Pratapgarh |
8130580 |
Amari Gram Panchayat Water Supply Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
173.57 |
16.84 |
16.84 |
0.00 |
156.73 |
173.57 |
Under Construction |
83.00 |
Work in Progress (T.well- 100%, Pump House-80%,Pipe Line- 80%, OHT-80%,FHTC-0/350) |
| 14 |
Pratapgarh |
8130588 |
Raipur Gram Panchayat Water Supply Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
232.72 |
0.41 |
0.41 |
0.00 |
232.31 |
232.72 |
Under Construction |
0.00 |
1.Due to Saline water Progress of work could not be continued. 2. DPR is being revised by identifying new land at nearby village for Tube Well with required Rising Main. 3.Revised DPR/Proposal shall be submitted by 30.11.2026. |
| 15 |
Pratapgarh |
8130665 |
Teliyani Gram Panchayat Water Supply Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
201.13 |
71.76 |
71.76 |
0.00 |
129.37 |
201.13 |
Under Construction |
81.00 |
Work in progress (T.well- 100%,Pump house-90%, Pipe Line- 40%, OHT-90%,FHTC-50/385) |
| 16 |
Pratapgarh |
8130687 |
Chaupai Gram Panchayat Water Supply Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
172.51 |
54.85 |
54.85 |
0.00 |
117.66 |
172.51 |
Under Construction |
85.00 |
Work in Progress (T.well- 100%,Pump House-90% Pipe Line- 85%, OHT-100%,FHTC-188/394) |
| 17 |
Pratapgarh |
8130701 |
Kadipur Gram Panchayat Water Supply Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
225.17 |
90.62 |
90.62 |
0.00 |
134.55 |
225.17 |
Under Construction |
80.00 |
Work in Progress(T.well- 100%, Pump House-90%,Pipe Line- 65%, OHT-95,FHTC-!80/416%) |
| 18 |
Pratapgarh |
8130712 |
Kishungarh Gram Panchayat Water Supply Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
190.27 |
43.77 |
43.77 |
0.00 |
146.50 |
190.27 |
Under Construction |
96.00 |
Major Work i.e T.Well, Pump House, OHT, Pipe Line, FHTC has been Completed. Development work of T.Well is in Progress which may be completed by 15/11/2026 after that Testing, Commissioning, of OHT, Pipe line Electro Mechanical equipments shall be completed within week and Scheme shall be made Operational by 20/11/2026 |
| 19 |
Pratapgarh |
8130726 |
Kadharpur Gram Panchayat Water Supply Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
189.74 |
12.85 |
12.85 |
0.00 |
176.89 |
189.74 |
Under Construction |
35.00 |
Work in Progress (T.well- 100%Pump HOuse-70% Pipe Line- 5%, OHT- 0%,FHTC-0/282) |
| 20 |
Pratapgarh |
8130825 |
Lohang Patti Gram Panchayat Water Supply Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
234.36 |
9.05 |
9.05 |
0.00 |
225.31 |
234.36 |
Under Construction |
35.00 |
Work of Progress (T.well- 100%,Pump House-95% Pipe Line- 20%, OHT-40%,FHTC-0/529) |
| 21 |
Pratapgarh |
8130860 |
Jagdishpur Gram Panchayat Water Supply Scheme |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
169.94 |
0.29 |
0.29 |
0.00 |
169.65 |
169.94 |
Under Construction |
0.00 |
1.Due to Saline water Progress of work could not be continued.
2. DPR is being revised by identifying new land at nearby village for Tube Well with required Rising Main. 3.Revised DPR/Proposal shall be submitted by 30.11.2026. |
| 22 |
Pratapgarh |
8131578 |
TALA SIRSABAD |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
193.90 |
0.49 |
0.49 |
0.00 |
193.41 |
193.90 |
Under Construction |
0.00 |
1.Due to Saline water Progress of work could not be continued.
2. DPR is being revised by identifying new land at nearby village for Tube Well with required Rising Main. 3.Revised DPR/Proposal shall be submitted by 30.11.2026. |
| 23 |
Pratapgarh |
8131586 |
PURAB GAON |
NRDWP |
Jal Nigam |
YES |
NO |
NO |
198.66 |
42.41 |
42.41 |
0.00 |
156.25 |
198.66 |
Under Construction |
93.00 |
Work in Progress (T.well- 100%,Pump House-65% Pipe Line- 86%, OHT-95%,FHTC-182/643) |
| 24 |
Pratapgarh |
8193967 |
KHAJURI |
SRDWP |
Jal Nigam |
YES |
NO |
NO |
168.54 |
0.26 |
0.26 |
0.00 |
168.28 |
168.54 |
Under Construction |
0.00 |
1.Due to Saline water Progress of work could not be continued.
2. DPR is being revised by identifying new land at nearby village for Tube Well with required Rising Main. 3.Revised DPR/Proposal shall be submitted by 30.11.2026. |