Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | Power Mech Projects Ltd | 20089241 | Akbarabad | 171.12 | 104.42 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | NA | 25 | Yes | No | 7508.00 | 7500.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | Devmai | Akbarabad | 427323 | Akbarabad | 271 | 271 | 100 | Har Gar Jal | Certified |
| 2 | Fatehpur | Devmai | Alampur | 427325 | Alampur | 306 | 306 | 100 | Har Gar Jal | Certified |
| 3 | Fatehpur | Devmai | Karanpur | 427331 | Karanpura | 541 | 541 | 100 | Har Gar Jal | Certified |
| 4 | Fatehpur | Devmai | Kashmiri Pur | 427333 | Kashmiripur | 337 | 177 | 53 | Work In Progress | Not Certified |
| 5 | Fatehpur | Devmai | Tikara | 427352 | Tikara | 369 | 369 | 100 | Har Gar Jal | Certified |
| 6 | Fatehpur | Devmai | Varigvan | 427370 | Varigawan | 515 | 515 | 100 | Har Gar Jal | Not Certified |