Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Auraiya | GVPR | 20088698 | Sanpher & Seopur PWS | 737.82 | 414.32 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 2 | 2 | 1 | 1 | 1 | 0 | 1 | 54 | 54 | Yes | 0 | NA | No | 28202.00 | 28202.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Auraiya | Ajitmal | Sanpher | 420616 | Sanpher | 894 | 879 | 98 | Work In Progress | Not Certified |
| 2 | Auraiya | Ajitmal | Seopur | 420617 | Seopur | 193 | 193 | 100 | Har Gar Jal | Not Certified |
| 3 | Auraiya | Ajitmal | Seopur | 420618 | Beri Kapariya | 209 | 209 | 100 | Har Gar Jal | Not Certified |