Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | AFCONS | 20064890 | DEORIA VILLAGE WATER SUPPLY SCHEME | 340.41 | 109.36 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 0 | 0 | 0 | 1 | 1 | 0 | 20 | 20 | No | 0 | NA | No | 25884.00 | 0.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Baksha | Deoria | 469083 | Deoria | 353 | 1 | 0 | Work In Progress | Not Certified |
| 2 | Jaunpur | Baksha | Deoria | 469084 | Nuruddinpur | 30 | 1 | 3 | Work In Progress | Not Certified |