| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | NCC Ltd. | 20020551 | Pati Dharamdas , Bhaisla | 297.89 | 201.90 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 24 | 24 | Yes | 0 | NA | No | 13126.00 | 13180.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Pali | Pati Dharamdas | 454839 | Pati Dharamdas | 108 | 108 | 100 | Har Gar Jal | Not Certified |
| 2 | Gorakhpur | Pali | Pati Dharamdas | 454840 | Kolhui | 18 | 12 | 67 | Work In Progress | Not Certified |
| 3 | Gorakhpur | Pali | Pati Dharamdas | 454841 | Bhelaur | 93 | 93 | 100 | Har Gar Jal | Not Certified |
| 4 | Gorakhpur | Pali | Bhaisla | 454842 | Bhaisla | 150 | 148 | 99 | Work In Progress | Not Certified |
| 5 | Gorakhpur | Pali | Bhaisla | 454843 | Koma | 4 | 1 | 25 | Work In Progress | Not Certified |
| 6 | Gorakhpur | Pali | Bhaisla | 454844 | Surdahi | 116 | 115 | 99 | Work In Progress | Not Certified |