Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sambhal | SPML Infra | 20018917 | GOVINDPUR WATER SUPPLY SCHEME | 249.16 | 159.49 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 23 | 23 | Yes | 0 | NA | No | 6701.00 | 6701.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sambhal | Pawasa | Nagalia Ballu | 388941 | Kadarpur | 161 | 161 | 100 | Har Gar Jal | Certified |
| 2 | Sambhal | Pawasa | Hindoli | 388947 | Hindoli | 423 | 423 | 100 | Har Gar Jal | Certified |
| 3 | Sambhal | Pawasa | Qasampur Jagrup | 388952 | Qasampur Jagrup | 356 | 354 | 99 | Work In Progress | Not Certified |
| 4 | Sambhal | Pawasa | Kaili | 388983 | Kaili | 451 | 451 | 100 | Har Gar Jal | Certified |
| 5 | Sambhal | Pawasa | Govindpur | 389004 | Govindpur | 614 | 614 | 100 | Har Gar Jal | Certified |