Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Bahraich | PNC-SPML-JV | 20012360 | KESHWAPUR BALAHA PWS | 363.37 | 240.97 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 1 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 27 | 27 | Yes | 0 | NA | No | 15084.00 | 15084.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bahraich | Balaha | Bhaluhiya Bharat | 441836 | Bhaluhiya Bharat | 360 | 360 | 100 | Har Gar Jal | Not Certified |
| 2 | Bahraich | Balaha | Matiha | 441840 | Matiha | 519 | 507 | 98 | Work In Progress | Not Certified |
| 3 | Bahraich | Balaha | Kakri | 441841 | Kakri | 589 | 589 | 100 | Har Gar Jal | Certified |
| 4 | Bahraich | Balaha | Kakraha Bodhawa | 441843 | Kakraha Bodhawa | 583 | 580 | 99 | Work In Progress | Not Certified |
| 5 | Bahraich | Balaha | Maheshpur | 441856 | Maheshpur | 469 | 469 | 100 | Har Gar Jal | Certified |
| 6 | Bahraich | Balaha | KESHWAPUR | 441872 | KESHAWAPUR | 697 | 697 | 100 | Har Gar Jal | Certified |