Project Completion Certificate (Ground Water)
Scheme ID: 8362284 Name of Scheme: Badhupura & Gajipura GOV Water Supply Scheme No. of Villages: 2 No. of Habitation Covered: 2
Total Population Covered: 3076 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 03-Mar-2025 Actual Date of Completion (Capex): 11-Jun-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 30.03/117.83 Badhupura 29.4735829 77.24074196
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 700LPM/63 mtr Badhupura 29.4735829 77.24074196
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 200Kl/16M Badhupura 29.4735829 77.24074196
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI Pipe 150 0.0286
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 3.873
2 HDPE 75 0.645
3 HDPE 90 0.445
4 HDPE 110 1.108
5 HDPE 160 0.392
6 HDPE 200 0.103
HSC Connection
Sno. Total Nos.
1 639
Other Details
1.88
0.00
1.92
11-Jun-2025
12-Jun-2025