Project Completion Certificate (Ground Water)
Scheme ID: 20100669 Name of Scheme: PORAI KHURD VILLAGE WATER SUPPLY SCHEME No. of Villages: 3 No. of Habitation Covered: 6
Total Population Covered: 4830 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 21-Feb-2024 Actual Date of Completion (Capex): 12-Oct-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 300 6 m/ 64.20 m Porai khurd 25.987052 82.709662
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 12.5 HP 700 LPM/43M Porai khurd 25.987052 82.709662
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 200 KL /12 M Porai khurd 25.986956 82.709559
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 Di,K-7 150 0.0194 Yes
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 90 1.378 yes
2 HDPE 75 2.548 yes
3 HDPE 63 5.707 yes
4 HDPE 110 .820 yes
5 HDPE 140 .779 yes
6 HDPE 160 .729 yes
7 HDPE 180 .435 yes
HSC Connection
Sno. Total Nos.
1 493
Other Details
2.32
2.32
2.07
12-Oct-2024
13-Oct-2024