Project Completion Certificate (Ground Water)
Scheme ID: 20100642 Name of Scheme: PURE EBADULLA WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 7
Total Population Covered: 2084 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 12-May-2024 Actual Date of Completion (Capex): 13-Jun-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBWELL 50.19/16 PURE EBADULLA 26.292190 81.714839
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE -1 440/52 PURE EBADULLA 26.292190 81.714839
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT - 1 125/14 PURE EBADULLA 26.292190 81.714839
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-7 100 0.025
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 7.903
2 HDPE 90 2.918
3 HDPE 110 1.613
4 HDPE 125 0.000
5 HDPE 140 4.266
6 HDPE 160 0.303
7 HDPE 180 0.054
8 HDPE 200 0.000
HSC Connection
Sno. Total Nos.
1 326
Other Details
2.99
0.00
2.97
13-Sep-2024
16-Dec-2024