Project Completion Certificate (Ground Water)
Scheme ID: 20099788 Name of Scheme: PARSA RAMPUR PHAKARPUR (VPL) PWS No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 2520 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 08-Dec-2024 Actual Date of Completion (Capex): 15-Oct-2026
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube well 24m/ 233.74m Paras Rampur 27.419178 81.518858
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VT Pump 0.55cum/min 45m head Paras Rampur 27.419178 81.518858
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Over Head Tank 150kl/ 12m Paras Rampur 27.419178 81.518858
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI-K9 100 0.030
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE-PN6 63 3.020
2 HDPE-PN6 75 0.250
3 HDPE-PN6 90 0.265
4 HDPE-PN6 110 0.398
5 HDPE-PN6 160 0.196
6 HDPE-PN6 200 0.061
HSC Connection
Sno. Total Nos.
1 225
Other Details
1.62
1.62
1.53
08-Aug-2026
20-Oct-2026