Project Completion Certificate (Ground Water)
Scheme ID: 20099156 Name of Scheme: TEEKAR MAFI & BALIPUR DUHIYA WATER SUPPLY SCHEME No. of Villages: 3 No. of Habitation Covered: 15
Total Population Covered: 9264 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 02-Jul-2024 Actual Date of Completion (Capex): 11-Jun-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 150MM PLAIN PIPE 07.00 TEEKAR MAFHI & BALIPUR 26.148472 81.918569
2 300MM PLAIN PIPE 133.00 TEEKAR MAFHI & BALIPUR 26.148472 81.918569
3 300MM SLOTTED PIPE 36.00 TEEKAR MAFHI & BALIPUR 26.148472 81.918569
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUMERSIBLE PUMP 975LPM / 56 MTR TEEKAR MAFHI & BALIPUR 26.148472 81.918569
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OVER HEAD TANK 550 KL / 18 MTR TEEKAR MAFHI & BALIPUR 26.148472 81.918569
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE 150 1.042
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE 90 2.93
2 HDPE PIPE 75 2.568
3 HDPE PIPE 63 44.888
4 HDPE PIPE 110 1.998
5 HDPE PIPE 140 0.669
6 HDPE PIPE 160 0.094
7 HDPE PIPE 200 1.942
8 DI PIPE 250 0.897
9 DI PIPE 300 0.034
HSC Connection
Sno. Total Nos.
1 1418
Other Details
9.65
0.00
9.65
10-Sep-2024
30-Dec-2024