| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20098332 | Name of Scheme: BABUPUR Water Supply Scheme | No. of Villages: 1 | No. of Habitation Covered: 10 |
| Total Population Covered: 3145 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 24-Apr-2024 | Actual Date of Completion (Capex): 25-Feb-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 27.09/75.22 | BABUPUR | 26.375235 | 81.648445 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBERMIBLE | 700/52 | BABUPUR | 26.375235 | 81.648445 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 200/14 | BABUPUR | 26.375235 | 81.648445 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI K-7 | 150 | 0.0236 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 9.094 | |
| 2 | HDPE | 90 | 2.504 | |
| 3 | HDPE | 110 | 1.482 | |
| 4 | HDPE | 140 | 0.469 | |
| 5 | HDPE | 180 | 0.044 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 583 |