Project Completion Certificate (Ground Water)
Scheme ID: 20097933 Name of Scheme: BASVA&GURSANDI No. of Villages: 2 No. of Habitation Covered: 3
Total Population Covered: 6980 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 26-Sep-2023 Actual Date of Completion (Capex): 30-Jun-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 18/98 BASWA GURSANDI 25".658042"N 81.088175"E
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 580/60 BASWA GURSANDI 25".658042"N 81.088175"E
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 200KL/16M BASWA GURSANDI 25".658042"N 81.088175"E
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I. K-9 125 0.018
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 200 0.03
2 HDPE 180 0.401
3 HDPE 160 0.8636
4 HDPE 140 2.9696
5 HDPE 125 0.215
6 HDPE 110 0.2695
7 HDPE 90 0.7933
8 HDPE 75 1.4656
9 HDPE 63 14.4632
HSC Connection
Sno. Total Nos.
1 1369
Other Details
4.62
0.00
4.61
10-Jun-2025
11-Jun-2025