Project Completion Certificate (Ground Water)
Scheme ID: 20096500 Name of Scheme: AKABARI GRAM PANCHAYAT VILLAGE WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 3040 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 20-Jul-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 21.00/94.00 AKABARI 28.127613 79.697401
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VP PUMP -1 37.74 M3 / 45 M AKABARI 28.127613 79.697401
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT -1 175 KL-12 M AKABARI 28.127698 79.697480
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 K-7 150 0.0295
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE / 6Kg 63 5.600
2 HDPE / 6Kg 75 0.588
3 HDPE / 6Kg 90 0.089
4 HDPE / 6Kg 110 0.065
5 HDPE / 6Kg 140 0.070
6 HDPE / 6Kg 160 0.306
HSC Connection
Sno. Total Nos.
1 496
Other Details
1.88
0.00
1.88
19-Oct-2024
06-Dec-2024