Project Completion Certificate (Ground Water)
Scheme ID: 20093182 Name of Scheme: KATIYA MVS No. of Villages: 2 No. of Habitation Covered: 3
Total Population Covered: 5925 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 30-Jun-2027 Actual Date of Completion (Capex): 12-Sep-2026
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 25M/107.30M KATIYA 27.56911 79.26573
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 1180LPM/63M KATIYA 27.56911 79.26573
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 350KL/16M KATIYA 27.56911 79.26573
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 150 0.020
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE 90 0.925
2 HDPE PIPE 63 6.442
3 HDPE PIPE 110 0.719
4 HDPE PIPE 140 1.548
5 HDPE PIPE 160 0.121
6 HDPE PIPE 180 0.466
7 HDPE PIPE 200 1.039
HSC Connection
Sno. Total Nos.
1 1280
Other Details
4.58
4.44
4.58
12-Sep-2026
13-Sep-2026