Project Completion Certificate (Ground Water)
Scheme ID: 20092876 Name of Scheme: MAU GRAM PANCHAYAT WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 6
Total Population Covered: 2570 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 18-Jul-2024 Actual Date of Completion (Capex): 27-Nov-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 22.02 M / 75.26 M Mau 26.411338 81.935443
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 363 LPM / 42 M Mau 26.411338 81.935443
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 100 KL / 12 M Mau 26.411338 81.935443
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI /K9 100 0.010
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE /PN6:Class PE-100 63 7.514
2 HDPE /PN6:Class PE-100 75 0.509
3 HDPE /PN6:Class PE-100 90 0.27
4 HDPE /PN6:Class PE-100 110 1.345
5 HDPE /PN6:Class PE-100 125 0.14
6 HDPE /PN6:Class PE-100 140 0.38
7 HDPE /PN6:Class PE-100 160 0.86
8 HDPE /PN6:Class PE-100 180 0.141
HSC Connection
Sno. Total Nos.
1 359
Other Details
1.48
0.00
1.51
28-Feb-2025
01-Apr-2025