Project Completion Certificate (Ground Water)
Scheme ID: 20092189 Name of Scheme: Mahdewa Jungle Water Supply Scheme No. of Villages: 1 No. of Habitation Covered: 3
Total Population Covered: 131 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 21-Oct-2024 Actual Date of Completion (Capex): 17-Sep-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 36.10/87.73 Mahdewa Jungle 26.6387 83.5816
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 18/39 Mahdewa Jungle 26.6387 83.5816
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Overhead Tank-1 75/12 Mahdewa Jungle 26.6387 83.5816
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 100 0.014 Laying Completed
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 6.104 Laying Completed
2 HDPE 75 0.558 Laying Completed
3 HDPE 90 0.066 Laying Completed
HSC Connection
Sno. Total Nos.
1 166
Other Details
1.18
0.00
1.28
16-Sep-2024
03-Oct-2025