| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20091682 | Name of Scheme: LAKHMI PUR & NINAUA MVS | No. of Villages: 3 | No. of Habitation Covered: 3 |
| Total Population Covered: 2662 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 30-May-2025 | Actual Date of Completion (Capex): 08-Jun-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 13.03 M / 106.80 M | LAKHMI PUR | 27.33981 | 79.57987 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | PUMP | 600 LPM / 61 M | LAKHMI PUR | 27.33981 | 79.57987 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 175 KL / 14 M | LAKHMI PUR | 27.33981 | 79.57987 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI / K-7 | 100 | .025 | COMPLETE |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 90 | 1.812 | COMPLETE |
| 2 | HDPE | 63 | 3.638 | COMPLETE |
| 3 | HDPE | 110 | .729 | COMPLETE |
| 4 | HDPE | 140 | 2.339 | COMPLETE |
| 5 | HDPE | 160 | .472 | COMPLETE |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 475 |