| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20091259 | Name of Scheme: BESERPUR TARAI | No. of Villages: 1 | No. of Habitation Covered: 7 |
| Total Population Covered: 3126 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 30-May-2025 | Actual Date of Completion (Capex): 07-Jul-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 24M/132m | BESERPUR TARAI | 27.43814 | 79.56071 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersibel Pump | 650LPM/61M | BESERPUR TARAI | 27.43814 | 79.56071 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 150KL/61M | BESERPUR TARAI | 27.43814 | 79.56071 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 100 | 0.0225 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 90 | 3.508 | |
| 2 | HDPE | 63 | 4.703 | |
| 3 | HDPE | 110 | 0.920 | |
| 4 | HDPE | 140 | 0.660 | |
| 5 | HDPE | 160 | 1.423 | |
| 6 | HDPE | 180 | 0.717 | |
| 7 | HDPE | 200 | 1.169 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 586 |