Project Completion Certificate (Ground Water)
Scheme ID: 20091217 Name of Scheme: MADHAVPUR GRAM PANCHAYAT WATER SUPPLY SCHEME No. of Villages: 3 No. of Habitation Covered: 4
Total Population Covered: 2796 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 22-Mar-2024 Actual Date of Completion (Capex): 29-Nov-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 21.99 M / 84.82 M Madhavpur 26.387986 82.092252
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 400 LPM / 44M Madhavpur 26.387986 82.092252
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 125 KL /12 M Madhavpur 26.387986 82.092252
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI / K7 100 0.020
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE / PN6:Class PE-100 63 13.542
2 HDPE / PN6:Class PE-100 75 0.935
3 HDPE / PN6:Class PE-100 90 0.404
4 HDPE / PN6:Class PE-100 110 0.302
5 HDPE / PN6:Class PE-100 140 0.248
HSC Connection
Sno. Total Nos.
1 405
Other Details
1.94
0.00
1.98
28-Feb-2025
01-Apr-2025