| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20086712 | Name of Scheme: Mairi GP Water Supply Scheme | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 2340 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 19-Nov-2024 | Actual Date of Completion (Capex): 14-Jul-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | MSERW PLAIN PIPE-200MM | 36M | MAIRI | 27.367505 | 83.672875 |
| 2 | MSERW SLOTTED PIPE-150 MM | 18 | MAIRI | 27.367505 | 83.672875 |
| 3 | MSERW PLAIN PIPE-150 MM | 75.2 | MAIRI | 27.367505 | 83.672875 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE PUMP | 26.99/39M | MAIRI | 27.367505 | 83.672875 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | ZINK ALM OHT | 150KL/14M | MAIRI | 27.367390 | 83.672730 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DOUBLE FLANGE DI-K9 | 150 | 0.0295 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | PN-6/PE-100/HDPE | 63 | 1.91 | |
| 2 | PN-6/PE-100/HDPE | 75 | 1.39 | |
| 3 | PN-6/PE-100/HDPE | 90 | 1.71 | |
| 4 | PN-6/PE-100/HDPE | 110 | 0.29 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 237 |