Project Completion Certificate (Ground Water)
Scheme ID: 20082322 Name of Scheme: NIHALPUR &ALINAGAR WATER SUPPLY SCHEME No. of Villages: 3 No. of Habitation Covered: 7
Total Population Covered: 4016 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 15-Sep-2024 Actual Date of Completion (Capex): 18-Jun-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 150MM PLAIN PIPE 10.3 NIHALPUR & ALINAGAR 26.477175 81.714511
2 300MM PLAIN PIPE 69 NIHALPUR & ALINAGAR 26.477175 81.714511
3 150MM SLOTTED PIPE 4 NIHALPUR & ALINAGAR 26.477175 81.714511
4 300MM SLOTTED PIPE 16 NIHALPUR & ALINAGAR 26.477175 81.714511
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUMERSIBLE PUMP 840LPM / 54MTR NIHALPUR & ALINAGAR 26.477175 81.714511
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OVER HEAD TANK 250KL / 16MTR NIHALPUR & ALINAGAR 26.477175 81.714511
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE 150 0.0326
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE 90 3.319
2 HDPE PIPE 63 11.789
3 HDPE PIPE 110 3.707
4 HDPE PIPE 160 1.252
5 HDPE PIPE 180 1.767
6 HDPE PIPE 200 0.608
HSC Connection
Sno. Total Nos.
1 665
Other Details
4.74
0.00
4.68
21-Sep-2024
05-Jan-2025