Project Completion Certificate (Ground Water)
Scheme ID: 20071929 Name of Scheme: KATGHARA WATER SUPPLY SCHEME No. of Villages: 3 No. of Habitation Covered: 4
Total Population Covered: 1580 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 05-Feb-2024 Actual Date of Completion (Capex): 18-Nov-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 18.00/82.80 KATGHARA 26.3444167 82.145504
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 330LPM/42M KATGHARA 26.3444167 82.145504
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 100KL/12M KATGHARA 26.3444167 82.145504
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-7 100 0.020
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PN-6 PE-100 63 7.883
2 HDPE PN-6 PE-100 75 0.829
3 HDPE PN-6 PE-100 90 0.272
4 HDPE PN-6 PE-100 110 0.126
5 HDPE PN-6 PE-100 140 0.027
HSC Connection
Sno. Total Nos.
1 590
Other Details
156.57
0.00
156.35
04-Mar-2026
13-Jul-2026