Project Completion Certificate (Ground Water)
Scheme ID: 20070202 Name of Scheme: MACHHRI Village water supply scheme No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 1137 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 27-Jan-2023 Actual Date of Completion (Capex): 01-Jan-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 30/102 MACHRI 28.820887 77.619522
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 580/56 MACHRI 28.820887 77.619522
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 175/10 MACHRI 28.820887 77.619522
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I 100 0.016 100% WORK DONE
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 3.865 100% WORK DONE
2 HDPE 75 0.187 100% WORK DONE
3 HDPE 90 0.207 100% WORK DONE
4 HDPE 110 0.277 100% WORK DONE
5 HDPE 140 0.054 100% WORK DONE
6 HDPE 160 0.291 100% WORK DONE
HSC Connection
Sno. Total Nos.
1 486
Other Details
1.63
1.68
1.68
31-Oct-2025
01-Nov-2025