Project Completion Certificate (Ground Water)
Scheme ID: 20068082 Name of Scheme: KISHUNI WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 5
Total Population Covered: 7071 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 09-Jan-2024 Actual Date of Completion (Capex): 19-Feb-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL-1 20.08/94.12 KISHUNI 26.584584 81.664660
2 TUBEWELL-2 20/96.12 KISHUNI 26.587505 81.644550
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE-1 700 LPM/56M KISHUNI 26.584584 81.664660
2 SUBMERSIBLE-2 700 LPM/56M KISHUNI 26.587505 81.644550
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT - 1 400KL/18 M KISHUNI 26.584584 81.664660
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-7 150 0.798
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 9.279
2 HDPE 90 6.876
3 HDPE 110 1.837
4 HDPE 125 0.165
5 HDPE 140 0.839
6 HDPE 180 0.241
7 HDPE 200 0.275
HSC Connection
Sno. Total Nos.
1 1398
Other Details
6.63
0.00
6.60
19-May-2025
20-Aug-2025