Project Completion Certificate (Ground Water)
Scheme ID: 20067762 Name of Scheme: KADI FARIDPUR Water Supply Scheme No. of Villages: 6 No. of Habitation Covered: 9
Total Population Covered: 3730 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 10-Mar-2024 Actual Date of Completion (Capex): 09-Jul-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Lowering of borewell Assembly 30.14M/65.05 Kadi Fareedpur 26.410762 83.050565
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 15 HP Submersible Pump 790LPM/44M Kadi Fareedpur 26.410762 83.050565
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 RCC 225KL/14MTR Kadi Fareedpur 26.410762 83.050565
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI-K7 100 0.040
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 90 1.622
2 HDPE Pipe PN-6: Class PE-100 75 3.006
3 HDPE Pipe PN-6: Class PE-100 63 15.044
4 HDPE Pipe PN-6: Class PE-100 110 1.491
5 HDPE Pipe PN-6: Class PE-100 160 0.453
6 HDPE Pipe PN-6: Class PE-100 180 0.515
7 HDPE Pipe PN-6: Class PE-100 200 1.335
HSC Connection
Sno. Total Nos.
1 447
Other Details
3.17
3.17
3.17
19-Aug-2025
18-Nov-2025