Project Completion Certificate (Ground Water)
Scheme ID: 20067488 Name of Scheme: ARKHAPUR Water Supply Scheme No. of Villages: 8 No. of Habitation Covered: 8
Total Population Covered: 6840 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 20-Feb-2024 Actual Date of Completion (Capex): 24-Jul-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Lowering of Tubewell Assembly 42.05/108.01 ARKHAPUR 26.54480825 82.64159462
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Ac Submersible Pump 25 HP 1.45/44 ARKHAPUR 26.54480825 82.64159462
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 RCC 425 Kl/14 M ARKHAPUR 26.54480825 82.64159462
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI-K7 200 0.04
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6:Class PE-100 90 0.672
2 HDPE Pipe PN-6:Class PE-100 75 0.879
3 HDPE Pipe PN-6:Class PE-100 63 13.825
4 HDPE Pipe PN-6:Class PE-100 110 0.839
5 HDPE Pipe PN-6:Class PE-100 140 1.414
6 HDPE Pipe PN-6:Class PE-100 160 0.437
7 HDPE Pipe PN-6:Class PE-100 180 0.909
8 HDPE Pipe PN-6:Class PE-100 200 1.339
HSC Connection
Sno. Total Nos.
1 1128
Other Details
4.10
4.10
4.82
25-Oct-2025
26-Oct-2025