| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20067141 | Name of Scheme: ATANAGAR, DHAKKHIN GAUN & MIJHUTR GRAM PANCHAYAT WATER SUPPLY SCHEME | No. of Villages: 3 | No. of Habitation Covered: 20 |
| Total Population Covered: 8570 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 18-Jul-2024 | Actual Date of Completion (Capex): 01-Mar-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 65.00 M / 162.13 M | Atanagar & Dakkin gav & Mijhuthi | 26.420049 | 82.043949 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible Pump | 570 LPM / 46 & 47 M | Atanagar & Dakkin gav & Mijhuthi | 26.420049 | 82.043949 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 350 KL / 14 M | Atanagar & Dakkin gav & Mijhuthi | 26.420049 | 82.043949 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI / K7 | 125 | 0.020 | |
| 2 | DI / K7 | 150 | 1.339 | |
| 3 | DI / K7 | 200 | 0.352 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE / PN-6:Class PE-100 | 63 | 13.527 | |
| 2 | HDPE / PN-6:Class PE-100 | 75 | 5.079 | |
| 3 | HDPE / PN-6:Class PE-100 | 90 | 1.668 | |
| 4 | HDPE / PN-6:Class PE-100 | 110 | 1.939 | |
| 5 | HDPE / PN-6:Class PE-100 | 125 | 1.283 | |
| 6 | HDPE / PN-6:Class PE-100 | 140 | 1.743 | |
| 7 | HDPE / PN-6:Class PE-100 | 160 | 0.714 | |
| 8 | HDPE / PN-6:Class PE-100 | 200 | 1.409 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 882 |