| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20066151 | Name of Scheme: DANDUPUR WATER SUPPLY SCHEME | No. of Villages: 2 | No. of Habitation Covered: 10 |
| Total Population Covered: 4421 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 03-Aug-2024 | Actual Date of Completion (Capex): 02-Jun-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | 300MM PLAIN PIPE | 51 | DANDUPUR | 26.466263 | 81.447118 |
| 2 | 150MM PLAIN PIPE | 73.3 | DANDUPUR | 26.466263 | 81.447118 |
| 3 | 150MM SLOTTED PIPE | 7 | DANDUPUR | 26.466263 | 81.447118 |
| 4 | 300MM SLOTTED PIPE | 19 | DANDUPUR | 26.466263 | 81.447118 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE PUMP | 950LPM / 54MTR | DANDUPUR | 26.466263 | 81.447118 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OVER HEAD TANK | 275KL / 16MTR | DANDUPUR | 26.466263 | 81.447118 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI PIPE | 150 | .027 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE PIPE | 90 | 1.892 | |
| 2 | HDPE PIPE | 75 | 1.145 | |
| 3 | HDPE PIPE | 63 | 13.273 | |
| 4 | HDPE PIPE | 110 | 2.925 | |
| 5 | HDPE PIPE | 125 | 1.206 | |
| 6 | HDPE PIPE | 140 | .54 | |
| 7 | HDPE PIPE | 180 | .148 | |
| 8 | HDPE PIPE | 200 | 1.514 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 829 |