Project Completion Certificate (Ground Water)
Scheme ID: 20065196 Name of Scheme: DAKKHIN GAON KYAR, DHANESHA RAJPUT WATER SUPPLY SCHEME No. of Villages: 2 No. of Habitation Covered: 14
Total Population Covered: 7428 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 08-Jan-2024 Actual Date of Completion (Capex): 17-Oct-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL - 1 104.84/26.08 DAKKHIN GAON KYAR, DHANESHA RAJPUT 26.606637 81.577544
2 TUBEWELL - 2 104.84/26.08 DAKKHIN GAON KYAR, DHANESHA RAJPUT 26.609300 81.575980
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE - 1 775 LPM/58M DAKKHIN GAON KYAR, DHANESHA RAJPUT 26.606637 81.577544
2 SUBMERSIBLE - 2 775 LPM/58M DAKKHIN GAON KYAR, DHANESHA RAJPUT 26.609300 81.575980
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT - 1 450 KL/20M DAKKHIN GAON KYAR, DHANESHA RAJPUT 26.606637 81.577544
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-7 150 0.640
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 10.033
2 HDPE 90 5.789
3 HDPE 110 1.361
4 HDPE 125 0.500
5 HDPE 140 0.776
6 HDPE 200 2.575
HSC Connection
Sno. Total Nos.
1 1116
Other Details
6.62
0.00
6.60
17-Jan-2025
18-Apr-2025