Project Completion Certificate (Ground Water)
Scheme ID: 20064158 Name of Scheme: Sikahila No. of Villages: 1 No. of Habitation Covered: 2
Total Population Covered: 3005 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 12-Jan-2023 Actual Date of Completion (Capex): 31-Dec-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube well 27.11/126.57 Sikahila 26.517037 79.65782
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 29.60/61 Sikahila 26.517037 79.65782
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 200/16 Sikahila 26.517037 79.65782
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 150 0.026 As per Site
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 4.25 As per Site
2 HDPE 75 2.09 As per Site
3 HDPE 90 0.706 As per Site
4 HDPE 110 0.700 As per Site
5 HDPE 140 0.342 As per Site
6 HDPE 160 0.730 As per Site
7 HDPE 180 1.106 As per Site
HSC Connection
Sno. Total Nos.
1 530
Other Details
2.26
2.38
2.38
31-Mar-2024
01-Apr-2024